What the Alberta queue did across 22 editions

AESO replaces its list every month, so each edition reads as a snapshot. Held against each other, 22 editions show what a single one cannot.

November 2025

19.2 GW had an in-service date. One month later, 1.4 GW did.

Between the October and November 2025 editions, AESO moved 23 data centre projects from Active to ISD Under Review and their in-service dates came off the list. The queue grew in the same month, from 37 entries to 39, and no request left the list at all. Nothing was cancelled out of the fall: the projects stayed, the dates went.

AESO's own status column shows it: "Active" fell from 30 entries to 7 and "ISD Under Review" rose from 2 to 29.

Dated capacity, Oct 2025 19.2GW
Dated capacity, Nov 2025 1.4GW
Change −92%

Queue capacity, and how much of it has a date

Nov 2025 2025-01 2026-10
Filed capacity Capacity carrying an in-service date

What slipped

14 entries have had an in-service date move later. Cumulative slip across them is 6,554 days, 18.0 years. Median 554 days.

Ref MW Slip Moved to
P3109 1,200 24 mo no date
P3078 75 24 mo 2029-01-15
P3075 45 23 mo 2026-08-01
P2953 75 21 mo 2027-03-26
P3102 950 20 mo no date
P3126 5 19 mo 2027-12-10
P2952 75 18 mo 2027-03-26
P3157 75 14 mo 2028-11-20
P3077 75 12 mo 2029-01-15
P3079 75 9 mo 2027-09-01
P3101 950 8 mo no date
P3141 0 8 mo 2027-08-06
P3112 450 8 mo no date
P3110 300 7 mo no date

What left

11 requests have left the list entirely, 4.7 GW between them.

Ref MW Last seen
P3124 1,000 2026-01
P3129 932 2026-01
P3146 800 2026-06
P3164 800 2026-06
P2979 283 2025-10
P2980 283 2025-10
P2981 283 2025-10
P2919 200 2025-06
P2615 75 2025-01
P2883 55 2025-04
P2999 10 2025-10
How this is compiled

Each AESO edition from 2025-01 to 2026-10 is read from AESO's own file and compared with the one before it.