Canadian data centre power · updated 2026-08-18

Data centre power, province by province

How long a data centre waits before it can draw power in each of Canada's 13 jurisdictions, and what has moved since. The answers differ because disclosure does: Alberta publishes a project-level list every month, and most other operators publish nothing comparable.

The gap

Power is measured in years. Your date is not.

Every bar is a published figure, read from the operator or the regulator that published it. The bars are the jurisdictions that will commit to a number at all.

  • 0 of 13 jurisdictions publish no grid timeline
  • 0 days, median slip on the one queue that does publish, across 20 editions

And then it moves. The median filed project on Alberta's list has pushed its in-service date out by 416 days, which is 1.1 years on top of whatever it was quoted.

A conditional figure covers a defined subset, not the general case: Alberta's 4 to 6 years is for the two projects already allocated capacity, and a new entrant has no published figure at all.

Jurisdiction System operator Publishes projects Grid Behind the fence Projects MW announced, not operating
Alberta AESO Project level 4–6 * 2–4 24 9,761.9
Ontario IESO Project level 3–5 n/a 16 1,744.2
British Columbia BC Hydro Nothing project level 3–5 * n/a 11 583
New Brunswick NB Power Project level n/a * 2–4 1 390
Saskatchewan SaskPower Nothing project level 1–2 * n/a 2 300
Quebec Hydro-Québec Nothing project level n/a * n/a 19 137
Manitoba Manitoba Hydro Nothing project level n/a * n/a 3 5.5
Nova Scotia Nova Scotia Power Project level n/a * n/a 0 0
Newfoundland and Labrador Newfoundland and Labrador Hydro No data centre load identified n/a * n/a 0 0
Prince Edward Island Maritime Electric No data centre load identified n/a * n/a 0 0
Yukon Yukon Energy Corporation No data centre load identified n/a * n/a 0 0
Northwest Territories Northwest Territories Power Corporation No data centre load identified n/a * n/a 0 0
Nunavut Qulliq Energy Corporation No data centre load identified n/a * n/a 0 0

Years are as published, not modelled; an asterisk marks a conditional figure. MW counts announced capacity not yet energized, which is a different set from an operator's own list and is never summed with it. How the figures reconcile.

Alberta AESO 9,761.9MW

Courting load loudly while the near-term connection queue is already spoken for.

  • 4–6years to grid power
  • 2–4years behind the fence
  • 24tracked projects

Publishes a project-level connection list.

Binding constraint. Alberta is the source of the 1,200 MW interim cap, and it is fully allocated and now superseded. Sequence: AESO rolled out Large Load Integration Phase I on 4 June 2025 with a 1,200 MW interim large load connection limit. 15 projects from 5 developers (4,800 MW) qualified; 1,200 MW was assigned to 2 projects from 2 developers; contracts executed October 2025 (deadline extended from 4 August to allow developers to assess the new provincial levy). Final result: P2936 GLDC Load 970 MW and P3083 Keephills Data Centre Phase I 230 MW. Nothing else received firm grid capacity.

Full Alberta record Updated 2026-08-16

Ontario IESO 1,744.2MW

Open door dressed in new gatekeeping: government now picks winners before IESO's technical process even starts.

  • 3–5years to grid power
  • n/ayears behind the fence
  • 16tracked projects

Publishes a project-level connection list.

Binding constraint. There is no Alberta-style cap and no Quebec-style block allocation. Ontario has never set an MW ceiling for data centres, never run an allocation call, and never declared a provincial moratorium. If you are looking for a single number, there isn't one. What binds is five separate things, and right now the sharpest two are legal limbo and municipal land use, not grid capacity per se. 1. Regulatory limbo, the top constraint as of 2026-08-01. Electricity Act s.28.1 has been in force since December 11, 2025 and prohibits connecting a "specified load facility" unless regulatory requirements are met.

Full Ontario record Updated 2026-08-16

British Columbia BC Hydro 583MW

Effectively closed to unsolicited load: capacity is capped and allocated by competitive call, not first-come-first-served.

  • 3–5years to grid power
  • n/ayears behind the fence
  • 11tracked projects

Publishes nothing at project level.

Binding constraint. A Statutory volume cap plus A Competitive allocation, and it is roughly 2x oversubscribed on the first round. B.C. Reg. 8/2026, s. 3, for the two-year period beginning 1 Feb 2026: BC Hydro "must not... make available for conventional data centre purposes more than a total of 100 MW of new electricity capacity," and not more than "300 MW of new electricity capacity" plus any unused conventional allocation for AI data centre purposes. So 400 MW total for all data centres in BC over two years. Separately 200 MW for hydrogen-for-export.

Full British Columbia record Updated 2026-08-16

New Brunswick NB Power 390MW

Open but non-committal: the utility says it can handle a specific 190 MW request but wants flexible, interruptible load, not firm baseload commitments.

  • n/ayears to grid power
  • 2–4years behind the fence
  • 1tracked projects

Publishes a project-level connection list.

Binding constraint. There is NO formal cap, NO moratorium and NO block-allocation process for data centre load in New Brunswick as of 2026-08-01. Nothing resembling Alberta's 1,200 MW interim cap or Quebec's allocation calls exists. That absence is itself the finding, and it has been tested twice in 2026: - 2026-06-11/17: Green MLA Megan Mitton moved a resolution for an immediate moratorium on big data centres. The government refused; when Mitton sought unanimous consent to extend the sitting to force a vote, Liberal members shouted "no" and the House adjourned without voting.

Full New Brunswick record Updated 2026-08-01

Saskatchewan SaskPower 300MW

Open and courting, but riding on coal-refurbishment and nuclear plans that are not yet built.

  • 1–2years to grid power
  • n/ayears behind the fence
  • 2tracked projects

Publishes nothing at project level.

Binding constraint. There is no capacity cap, no moratorium, and no allocation round in Saskatchewan. Nothing equivalent to Alberta's 1,200 MW interim cap or Quebec's block allocation calls exists. The binding constraints are different in kind: 1. Dispatchable baseload availability, not headroom on paper. SaskPower has roughly 5,900 MW installed against average system demand of about 2,600-3,500 MW seasonally, but the province's own framing is that new AI load depends on firm always-on supply.

Full Saskatchewan record Updated 2026-08-01

Quebec Hydro-Québec 137MW

Went from selling surplus hydro to data centres to actively pricing and gatekeeping them out.

  • n/ayears to grid power
  • n/ayears behind the fence
  • 19tracked projects

Publishes nothing at project level.

Binding constraint. There is no numeric cap and no moratorium. The binding constraint is Discretionary ministerial allocation of a scarce energy balance, compounded by very thin local transmission headroom. It is not comparable to Alberta's 1,200 MW interim cap, it is looser on paper and tighter in practice. Correction to the premise: Quebec has Not run block allocation calls for data centre load. The only block RFP Hydro-Québec has ever run in this space was the 300 MW non-firm block for "cryptographic use applied to blockchains," launched 5 June 2019 following Régie decision of 29 April 2019, crypto mining only, not data centres.

Full Quebec record Updated 2026-08-01

Manitoba Manitoba Hydro 5.5MW

Closed to unsolicited large load: government now picks which projects get power, and it has already said no to at least one data centre.

  • n/ayears to grid power
  • n/ayears behind the fence
  • 3tracked projects

Publishes nothing at project level.

Binding constraint. Discretionary ministerial allocation plus a hard capacity wall, not a numeric cap. There is no Manitoba equivalent of Alberta's 1,200 MW interim cap and no Quebec-style block allocation call for data centre load. The binding constraints, in order: 1. Ministerial priority gate (in force 1 Sept 2025). Every >5 MW request is ranked low/medium/high by the Minister; low-priority requests are deferred behind all medium and high requests and served only if capacity would not be impaired; no appeal. M.R. 68/2025 ss.7-13. This is a political allocation decision, not a technical one, and no allocated volume is published.

Full Manitoba record Updated 2026-08-16

Nova Scotia Nova Scotia Power 0MW

Not actively pursuing data centres: the Premier says the file does not exist yet and won't until offshore wind is built.

  • n/ayears to grid power
  • n/ayears behind the fence
  • 0tracked projects

Publishes a project-level connection list.

Binding constraint. No formal cap and no allocation process, and that is itself the finding. Nova Scotia has nothing equivalent to Alberta's 1,200 MW interim cap or Quebec's block allocation calls. There is no moratorium, no queue cap, no data-centre allocation call, no large-load tariff. The binding constraint is physical scarcity plus political unwillingness, mediated by an undefined process. 1. System scale. Nova Scotia's all-time record system peak was 2,459 MW on 25 Jan 2026. A single 100 MW data centre is ~4% of provincial peak; the 325 MW IRL01 request is ~13%.

Full Nova Scotia record Updated 2026-08-01

Newfoundland and Labrador Newfoundland and Labrador Hydro 0MW

No data centre policy exists; the province is preoccupied with Gull Island/Churchill Falls megaproject planning and general industrial load growth, not data centre-specific rules.

  • n/ayears to grid power
  • n/ayears behind the fence
  • 0tracked projects

No data centre load identified.

Full Newfoundland and Labrador record Updated 2026-08-01

Prince Edward Island Maritime Electric 0MW

Not a data centre jurisdiction: the utility is import-dependent and adding peaking capacity for general demand growth, with no data centre-specific framework.

  • n/ayears to grid power
  • n/ayears behind the fence
  • 0tracked projects

No data centre load identified.

Full Prince Edward Island record Updated 2026-08-01

Yukon Yukon Energy Corporation 0MW

No real capacity to offer: a hydro-dominant but small, isolated grid where any large industrial-scale load requires a dedicated 20-25 year supply plan and new generation before connection.

  • n/ayears to grid power
  • n/ayears behind the fence
  • 0tracked projects

No data centre load identified.

Full Yukon record Updated 2026-08-01

Northwest Territories Northwest Territories Power Corporation 0MW

Not a viable near-term data centre jurisdiction: roughly two-thirds diesel generation, no surplus firm hydro capacity, and no data centre policy of any kind.

  • n/ayears to grid power
  • n/ayears behind the fence
  • 0tracked projects

No data centre load identified.

Full Northwest Territories record Updated 2026-08-01

Nunavut Qulliq Energy Corporation 0MW

Not a data centre jurisdiction under any definition: almost all electricity is diesel generated, with no inter-community grid at all.

  • n/ayears to grid power
  • n/ayears behind the fence
  • 0tracked projects

No data centre load identified.

Full Nunavut record Updated 2026-08-01

The record

What changed, month by month

What we record as it moves: changes in a connection queue, regulatory decisions, and company announcements. 190 entries, compiled 2026-08-18.

Show

This edition

What changed in August 2026

  • 6 Policy
  • 1 Announcement
  • 1 Joined the queue
  • 1 Given a date

9 entries, across AB, BC, ON.

Dated ahead

August 2026 Current edition 9 entries
  1. Policy AB

    AUC oral hearing commences (9 a.m., virtual) on the Indus Project Thermal Power Plant, Proceeding 30524: 1,494 MW of natural gas thermal generation supplying about 1,200 MW to co-located on-site data halls in Rocky View County.

    With the Heartland application below, these are the first gigawatt-class power plant applications of Alberta's bring-your-own-generation era to reach hearing. Status on the run date: under review.

  2. Policy AB

    AUC written hearing under way on the Heartland Project Thermal Power Plant, Proceeding 30518: 920 MW total capability supplying about 800 MW to co-located on-site data halls in Sturgeon County, filed under the Hydro and Electric Energy Act.

    The posted schedule ran to the applicant's final written reply evidence on 2026-08-04; no disposition has been posted. Status on the run date: under review.

  3. Policy BC

    BC Hydro's Call for Demand for Emerging Industries: intake closed, results pending.

    The utility states it “received 15 applications representing close to 800 megawatts (MW) in total load request” and expects to notify successful applicants by mid-September 2026. Against a two-year allocation target of up to 400 MW, that is roughly twice the available allocation, now confirmed in the utility's own figures rather than inferred. Captured from the BC Hydro page at browser level on 2026-08-16; see the source note on this card about the two versions that URL serves.

  4. Announcement AB

    Heartland Power Generation LP announces 800 MW at Alberta Industrial Heartland — Section 15, Township 56, Range 22, W4M; ~7 km east of Gibbons, Sturgeon County, AB

    Beacon AI Centers — Heartland Project Thermal Power Plant

  5. Policy ON

    Ontario announces its Data Centre Playbook and opens a 30-day public comment period, through the Environmental Registry of Ontario and the Ontario Regulatory Registry, on how large-scale data facilities connect to the grid.

    The government's own framework document is a draft: it calls itself the “Draft Data Centre Playbook”, says it is “under development”, and applies to data centres “that meet thresholds to be set out in a future regulation under the Electricity Act”. It is a framework and a consultation, not a filed regulation. The Playbook is anchored in three core principles for approving data centre connections to the grid, verbatim: (1) “Data centres must invest substantially, both financial and non-financial, in Ontario and local communities”; (2) “Data centres pay the full cost of electricity costs”; (3) “Ontario will only offer non-financial support to attract data centre investments”. Separately, and not to be confused with those principles, the document sets out three Strategic Priority Assessment pillars: Advance Economic Development; Protect Data Security and Digital Sovereignty; Invest in Communities and Earn Public Confidence.

  6. Policy ON

    Oakville Council passes an Interim Control By-law at a special council meeting, restricting new data centres, enterprise computing facilities and similar high-intensity digital processing facilities for one year, extendable to two, under Section 38 of the Planning Act.

    Reported alongside it: a similar bylaw failed in Hamilton and a final vote is pending in Mississauga. Municipal land use remains a live constraint on Ontario siting independent of provincial connection policy.

  7. Joined the queue AB P3198

    Lynx Data Load joins the Alberta queue at 1,800 MW

    P3198 appears on AESO's connection list for the first time in the 2026-08 edition.

  8. Given a date AB P3114

    Banshee Data MPC Load is given a grid date of 2027-11-01

    AESO issued an in-service date for P3114 at 75 MW. Only a minority of the queue carries one.

  9. Policy BC

    Status as of today: BC Hydro's Emerging Industries page reports the 2026 Call for Demand received 15 applications representing close to 800 MW of total load request.

    BC Hydro states it is currently reviewing applications and expects to notify successful applicants by mid-September 2026.

July 2026 18 entries
  1. Policy ON

    Mississauga council votes unanimously for an Interim Control By-Law pausing approvals of new AI data centre developments city-wide for up to one year, extendable a further year, the first such municipal pause in Ontario.

  2. Policy ON

    Minister of Energy and Mines Stephen Lecce states that data centres seeking grid access must demonstrate community benefits, pay the full cost of the electricity they consume, and meet provincial priorities: 'It is not your right'; 'if a data centre wants to e…

  3. Policy ON

    Reported that the IESO is applying its new large computational load reliability standards, including the revised voltage ride-through standard governing when a large computational load must stay connected during a voltage disturbance and when uninterruptible-power-supply-supported demand may partially or fully transfer from the grid.

  4. Policy ON

    IESO holds its public engagement webinar on the large computational load technical requirements, presenting stakeholder feedback and revised requirements posted July 15.

    Final feedback deadline July 31, 2026.

  5. Policy NB

    Miramichi city council pauses its proposed zoning bylaw amendment that would have permitted data centres and battery energy storage in Heavy Industrial zones, and cancels the public hearing scheduled for 2026-08-04, directing staff to seek expert opinion and p…

  6. Policy AB

    AESO posts Consolidated Stakeholder Feedback on the proposed BYOG process; final process rollout targeted for August 2026, first intake anticipated late 2026, with Phase 2B (ISO tariff) and Phase 2C (grid partners) consultations to follow.

  7. Announcement AB

    Teton Digital LLC announces 200 MW at ~35 km south of Fox Creek, AB

    Northern Forge Power Project (data centre power supply)

  8. Policy NB

    The province formally rules out a data centre ban but signals unspecified limits on future development.

    Spokesperson Jennifer MacNeil states, "These centres are essential to Canada's future, especially in supporting data sovereignty," and, "Data centres will be need to be designed and operated in a manner that does not put additional pressure on the electricity grid or rate payers."

  9. Policy QC

    BLG publishes 'Data centre regulation in Québec: from honeyed promise to iron control,' documenting the Rate LG ramp-up underperformance charge: Hydro-Québec reviews a customer's usage over the previous 12 billing periods, and if the customer's maximum power demand during that period is less than 60% of the reserved capacity, a charge applies.

    The article notes that several data centre operators have challenged the validity of this charge before the Québec Superior Court, with the outcome still pending.

  10. Announcement AB

    Meta Platforms Inc. announces 970 MW at Sturgeon County (Alberta's Industrial Heartland), AB

    Meta Data Center (Sturgeon County)

  11. Policy BC

    Black Press / Nelson Star reporting establishes that the new provincial data centre rules do not apply in FortisBC's private-utility service area, because B.C. Reg.

    8/2026 binds only BC Hydro.

  12. Announcement ON

    Undisclosed applicant announces 20 MW at 3110 South Service Rd, Burlington (former Mother Tucker's / Tucker's Marketplace site)

    Burlington Data Centre (3110 South Service Rd)

  13. Policy SK

    SaskPower receives federal approval to build two new interconnection lines into the United States, boosting export and import capacity, the implementation of the Energy Security Strategy's intertie expansion (SPP tie moving from 150 MW toward 650 MW by 2027).

  14. Joined the queue AB P3175

    Beacon Heartland Data Load joins the Alberta queue at 400 MW

    P3175 appears on AESO's connection list for the first time in the 2026-07 edition.

  15. Left the queue AB P3146

    Hanna MPC Data Load leaves the queue, 800 MW

    P3146 was flagged Recently Cancelled and no longer appears from the 2026-07 edition.

  16. Left the queue AB P3164

    Fort McMurray MPC Data Load leaves the queue, 800 MW

    P3164 was flagged Recently Cancelled and no longer appears from the 2026-07 edition. Filed in stages: 400 MW at EN1, 400 MW at EN2.

  17. Slipped AB P3157

    Clearwater Technology Park Data Load slips 14 months, to 2028-11-20

    The in-service date for P3157 moved from 2027-10-01 to 2028-11-20 between the 2026-06 and 2026-07 editions.

  18. Slipped AB P3126

    Sollair Load slips 3 months, to 2027-12-10

    The in-service date for P3126 moved from 2027-08-27 to 2027-12-10 between the 2026-06 and 2026-07 editions.

June 2026 17 entries
  1. Policy QC

    Government of Quebec launches its first Plan de gestion intégrée des ressources énergétiques (PGIRE) 2026-2050, required by Bill 69.

  2. Policy AB

    AESO publishes the Proposed BYOG Process (following a 24 June 2026 industry session): ~6-week intakes roughly every nine months, C$15,000/MW DTS commitment, 3–6 month connection studies, tethered gas-fired generation sized to full demand, 1,600 MW system-wide…

  3. Policy NS

    IESO Nova Scotia publishes the 2026 10-Year System Outlook Report.

    Section 5.2.2 and Table 8 disclose nine large-load System Impact Studies totalling ≈854.6 MW (IRL01-IRL10, IRL07 absent), the only project-level large-load disclosure in the province.

  4. Policy NS

    The premier of Nova Scotia says his government is not actively pursuing data centre projects, and he would only support such an endeavour if the province could fully supply the energy a data centre needs.

    Premier Tim Houston said, "There wouldn't be a commitment to a data centre unless we could fully supply the energy without any risk to Nova Scotians. It would only be something that would be done safely and would benefit Nova Scotians."

  5. Policy SK

    MLT Aikins legal insight on AI data centres in Canada states that Saskatchewan 'does not have a deregulated wholesale electricity market, and data centre developers cannot simply negotiate PPAs with independent generators unless they secure a consent from SaskPower.'

  6. Policy NB

    The Holt government refuses the data centre moratorium.

    Mitton's resolution never reaches a vote, when she seeks unanimous consent to extend the sitting to 6 p.m. to force one, Liberal members shout "no" and the House adjourns.

  7. Policy NS

    IESO NS/NSPI publish the current OASIS interconnection queues (Combined T/D Advanced Stage, Active Transmission, Active Distribution).

    Every row is Wind, Solar, Tidal, Battery or Gas Turbine, no load entries.

  8. Policy AB

    AESO publishes the Guide to AESO Connection Requirements for Transmission-Connected Data Centres.

  9. Policy NB

    About 150 protesters rally at the New Brunswick legislature on June 11, 2026 against the 390 MW Lorneville data centre project.

    They support Tantramar MLA Megan Mitton's resolution calling on the Holt government to stop development of big data centres until it passes legislation ensuring they will not increase the price of electricity, hurt communities or harm the environment. When Mitton sought unanimous consent to extend the sitting for a vote, several Liberal members refused, the legislature adjourned without voting, and the House began its summer recess the next day.

  10. Policy AB

    Data Centre Regulation, AR 117/2026, filed under the Electric Utilities Act, defines large data centres as transmission-connected loads requesting 75 MW or more of DTS and codifies bring-your-own-generation/tethering.

    It also lets the AESO lower the 75 MW threshold if needed, and lets the AESO aggregate two or more data centres under 75 MW that are co-located and share some ownership affiliation, considering them together as one data centre.

  11. Policy SK

    University of Regina Johnson Shoyama Graduate School of Public Policy brief by Justin Longo and Margot Hurlbert assesses the Regina-area AI data centre against SaskPower's roughly 5,900 MW installed capacity and 2,600-3,500 MW average seasonal demand, noting that a single 300 MW load is comparable to the BHP Jansen potash mine, one of the largest industrial developments in the province's history, and that SaskPower is already under significant pressure.

  12. Policy MB

    Premier Wab Kinew announces Manitoba will not approve the Jet.AI / Consensus Core hyperscale AI data centre on 142 hectares near Île-des-Chênes southeast of Winnipeg, citing environmental threat and limited economic benefit.

  13. Slipped AB P3141

    Opal Data Load slips 6 months, to 2027-08-06

    The in-service date for P3141 moved from 2027-02-11 to 2027-08-06 between the 2026-05 and 2026-06 editions.

  14. Policy NL

    NL Hydro's planning materials confirm the Labrador Network Additions Policy governs how new transmission costs for large load requests are allocated.

  15. Policy MB

    Bill 39, The Manitoba Hydro Amendment and Tax Administration and Miscellaneous Taxes Amendment Act, enacted as SM 2026, c.32, creates separate treatment for cryptocurrency operations, data centres and prescribed large power supply projects.

    Section 110.2(1) imposes a levy on such customers' total monthly electricity charges at a rate prescribed by regulation, or, if no rate is prescribed, at a rate equal to 100% of the monthly energy charge per kWh plus 100% of the monthly demand charge per kVA under the applicable General Service rate schedule.

  16. Policy MB

    Bill 20, The Manitoba Hydro Amendment Act, enacted as SM 2026, c.17, authorizes Manitoba Hydro to establish a curtailable power program for cryptocurrency operations.

    Under section 49.3, the program may be established to maintain the reliability, safety or adequacy of Manitoba's electricity system or to manage peak demand or system constraints, and it lets the corporation temporarily reduce the supply of power to a customer or class of customers using the power for cryptocurrency operations, in accordance with the program's terms and conditions.

  17. Policy QC

    Current revision of Hydro-Québec form 963-3367 'Development project of 5 MW or more', version (2026-06). Adds/retains Appendix 2 for data centres (category incl.

    Hyperscale; use incl.

May 2026 12 entries
  1. Policy NS

    IESO Nova Scotia publishes 2026 Integrated Resource Plan Assumption Set 1 (revised).

    Large Loads Base case: 'No significant new industrial loads beyond already announced projects.' Data centres appear only in the High sensitivity: 'Increased demand from new in…

  2. Policy ON

    IESO launches the Major Projects Identification Committees (MPIC) process, a voluntary early-identification intake for large projects (reported threshold 10 MW and above) to improve demand forecasting and assess readiness for connection.

  3. Policy NB

    Government of New Brunswick releases the NB Power Comprehensive Review Action Plan, 50 recommendations, 44 accepted, 6 requiring further analysis.

    Two matter for large loads.

  4. Announcement ON

    BUZZ High Performance Computing Inc. announces 320 MW at Greater Toronto Area, ON (exact municipality not disclosed)

    BUZZ HPC Greater Toronto Area AI Gigafactory

  5. Announcement BC

    Telus, in partnership with Government of Canada announces 85 MW at Kamloops, BC

    Telus Kamloops sovereign AI data centre (expansion)

  6. Announcement BC

    Telus announces at Vancouver, BC (Mount Pleasant)

    Telus AI data centre -- Mount Pleasant (M3 building, 111 East 5th Ave)

  7. Announcement BC

    Telus announces at Vancouver, BC (Yaletown / 150 West Georgia St)

    Telus AI data centre -- Yaletown (150 West Georgia St)

  8. Policy QC

    MEIE's official '5 MW and more' authorization process page describes dual filing to Formulaireprojet5MW@hydroquebec.com and blocselectricite@economie.gouv.qc.ca.

    All projects, without exception, are analyzed simultaneously by Hydro-Québec and the Ministry to minimize processing delays, and the process has three possible outcomes: refusal (the project is not accepted, but a new application may be filed), deferral (the request stays active and pending, with a meeting available to discuss elements needing improvement), or preliminary approval (pre-authorized projects must then follow further steps set out by the government).

  9. Given a date AB P3077

    Calgary Enterprise A.I. Load is given a grid date of 2029-01-15

    AESO issued an in-service date for P3077 at 75 MW. Only a minority of the queue carries one.

  10. Given a date AB P3078

    Calgary A.I. Centre Load is given a grid date of 2029-01-15

    AESO issued an in-service date for P3078 at 75 MW. Only a minority of the queue carries one.

  11. Policy NS

    NS Power 2026-2027 General Rate Application rates take effect (NSEB approved 25 Mar 2026): average increases of 1.2% in 2026 and 2.5% in 2027.

  12. Policy ON

    IESO posts draft Technical Requirements for Large Computational Loads Connecting to the Ontario Power System, adding performance requirements the Market Rules did not previously carry for AI and cryptocurrency facilities.

April 2026 9 entries
  1. Policy SK

    Policy Options (IRPP) analysis by Ben Beveridge argues Saskatchewan 'lacks a standing framework that applies the investment logic systematically' to Crown megadeals, and that 'the industrial power rate and the capital cost of Crown infrastructure being deployed have not been disclosed to the legislature or to ratepayers.' The piece notes that performance guarantees and full partnership terms also remain undisclosed, and calls for a standing disclosure requirement.

  2. Announcement MB

    Bell Canada announces 6 MW at 400 Goldenrod Drive, Rosser (CentrePort Canada), RM of Rosser, Manitoba

    Bell AI Fabric Rosser (CentrePort)

  3. Policy SK

    Boundary Dam Unit 4 is physically returned to service, restoring 150 MW of dispatchable baseload for $7.6 million after being in lay-up since 2021 and shut down in late 2024.

    Directly tied by the province to the Bell data centre load.

  4. Policy AB

    AESO posts the LLWG-2A BYOG Draft Front-End Process to AESO Engage.

  5. Policy NB

    New NB Power Rate Schedules and Policies take effect following the NBEUB decision in Matter EL-003-2025 (2026-27 General Rate Application).

  6. Slipped AB P3079

    Captus Load slips 9 months, to 2027-09-01

    The in-service date for P3079 moved from 2026-12-01 to 2027-09-01 between the 2026-03 and 2026-04 editions.

  7. Policy QC

    Bill 69 rate provisions (ss. 93, 107, 110, 129, 146-148, 150-152, 154) come into force. Rate L is abolished;

    Rate LG (general rate for large-power customers, minimum billing demand ≥5,000 kW) governs, with the 2026 rate schedule effective the same date.

  8. Policy NL

    Provincial government acts to reduce a scheduled July 1 electricity rate increase; unrelated to any large-load or data centre driver.

  9. Announcement AB

    Teton Digital LLC announces 466 MW at ~19 km south of Swan Hills, AB

    Black Bear Power Project (data centre power supply)

March 2026 20 entries
  1. Policy QC

    As-of date of the MEIE authorized-blocks tally: 30 electricity blocks totalling approximately 1,500 MW authorized for industrial projects since 2023 (four marked cancelled), plus approximately 800 MW across 55 public-interest projects.

  2. Policy SK

    SaskPower files details of its Coal Modernization Program in response to the Saskatchewan Rate Review Panel, setting out a unit-by-unit repowering schedule: Boundary Dam Unit 6 (Phase I in 2028, Phase II in late 2029 and 2030), Poplar River Unit 0/2 in 2031, Shand Unit 1 in 2032, Poplar River Unit 1 in 2033, Boundary Dam Unit 3 in 2034, Boundary Dam Unit 5 (Phase I in late 2027 and early 2028, Phase II in 2035), and Boundary Dam Unit 4 in 2035.

    SaskPower notes these dates are subject to change, with additional extension work ongoing outside the dates given.

  3. Policy SK

    Government of Saskatchewan approves SaskPower's North-South Transmission Systems Interconnection Project, which will link the province's separate northern and southern grids for the first time.

  4. Policy SK

    SaskPower confirms to media the interconnection build for the Bell facility: 'We will be constructing a total of 300 MW of power interconnection capacity to the facility.

  5. Announcement SK

    Bell Canada announces 300 MW at Rural Municipality of Sherwood No. 159, near Regina, Saskatchewan

    Bell AI Fabric — RM of Sherwood

  6. Policy BC

    Call for Demand application intake closes.

    The published milestone table sets initial applications and bid security at 2026-03-09, with failure to meet the date resulting in ineligibility; feasibility study results to shortlisted applicants 2026-08-11; supplemental applications 2026-08-25; withdrawal without forfeiting bid security 2026-09-01; outcome notification mid-September 2026. All dates are subject to change. The Request for Applications sets the size of an eligible request at 10 MW or greater and not more than 145 MW, and states that unsuccessful applicants “will not be eligible to enter the interconnection queue to enable interconnection to the BC Hydro System, or will be removed from the interconnection queue, if applicable”. Losing this competition does not mean waiting longer; it means leaving the queue.

  7. Policy BC

    Initial application deadline for the 2026 Call for Demand (11:00 a.m. Pacific).

    BC Hydro's Q&A confirms no extensions, and that a multi-phase project totalling 10 MW or more must come through the Call for Demand rather than the standard connection process.

  8. Announcement ON

    Logistics Land Investments announces 720 MW at Milton (farmland near Halton Hills Generating Station)

    Milton Hyperscale Data Centre (proposed, near Halton Hills Generating Station)

  9. Given a date AB P3108

    Wild Rose Power Hub Load is given a grid date of 2028-01-01

    AESO issued an in-service date for P3108 at 1,300 MW. Only a minority of the queue carries one.

  10. Given a date AB P3109

    Newell Data Center MPC Load is given a grid date of 2029-12-01

    AESO issued an in-service date for P3109 at 1,200 MW. Only a minority of the queue carries one.

  11. Given a date AB P3101

    Carstairs Technology Park MPC Load is given a grid date of 2029-01-01

    AESO issued an in-service date for P3101 at 950 MW. Only a minority of the queue carries one.

  12. Given a date AB P3102

    Goldfinch Technology Park MPC Load is given a grid date of 2029-01-01

    AESO issued an in-service date for P3102 at 950 MW. Only a minority of the queue carries one.

  13. Given a date AB P3116

    Rocky View Data Center MPC Load is given a grid date of 2029-12-01

    AESO issued an in-service date for P3116 at 800 MW. Only a minority of the queue carries one.

  14. Given a date AB P3146

    Hanna MPC Data Load is given a grid date of 2029-12-01

    AESO issued an in-service date for P3146 at 800 MW. Only a minority of the queue carries one.

  15. Given a date AB P3112

    North Calgary Three Data Centre MPC Load is given a grid date of 2028-03-08

    AESO issued an in-service date for P3112 at 450 MW. Only a minority of the queue carries one.

  16. Given a date AB P3110

    Mihta Askiy Data Load is given a grid date of 2027-02-08

    AESO issued an in-service date for P3110 at 300 MW. Only a minority of the queue carries one.

  17. Given a date AB P3156

    High Plains East Industrial Park is given a grid date of 2029-10-21

    AESO issued an in-service date for P3156 at 300 MW. Only a minority of the queue carries one.

  18. Given a date AB P3077

    Calgary Enterprise A.I. Load is given a grid date of 2028-01-15

    AESO issued an in-service date for P3077 at 75 MW. Only a minority of the queue carries one.

  19. Given a date AB P3078

    Calgary A.I. Centre Load is given a grid date of 2028-01-15

    AESO issued an in-service date for P3078 at 75 MW. Only a minority of the queue carries one.

  20. Policy ON

    IESO publishes the 2026 Annual Planning Outlook (Ontario's electricity system needs 2027-2050). Reference demand growth 65% to 2050 (high case 92%, low 38%);

    8 TWh energy need emerging in 2032; no significant incremental capacity needs until the mid-2030s; ove…

February 2026 10 entries
  1. Announcement AB

    CPP Investments / Brookfield announces 230 MW at Keephills, Parkland County, AB

    Keephills Data Centre (Phase I)

  2. Policy QC

    Hydro-Québec press release announcing Rate CD at an average ~13 ¢/kWh (about double large-power) and a revised blockchain Rate CB at ~19.5 ¢/kWh with three-year transition.

  3. Announcement BC

    DMG Blockchain Solutions Inc. announces 65 MW at Christina Lake, BC

    DMG Blockchain Christina Lake Data Center

  4. Policy MB

    Manitoba Hydro files its 2025 Integrated Resource Plan Report with the Public Utilities Board on February 2, 2026.

    CEO Allan Danroth states, "This filing represents the beginning of the final phase of IRP approval." The provincial government had requested the filing as part of the overall approval process.

  5. Joined the queue AB P3164

    Fort McMurray MPC Data Load joins the Alberta queue at 800 MW

    P3164 appears on AESO's connection list for the first time in the 2026-02 edition. Filed in stages: 400 MW at EN1, 400 MW at EN2.

  6. Joined the queue AB P3157

    Clearwater Technology Park Data Load joins the Alberta queue at 75 MW

    P3157 appears on AESO's connection list for the first time in the 2026-02 edition.

  7. Joined the queue AB P3174

    Sovereign Cloud Data Load joins the Alberta queue at 75 MW

    P3174 appears on AESO's connection list for the first time in the 2026-02 edition.

  8. Left the queue AB P3124

    Evarts Data Load leaves the queue, 1,000 MW

    P3124 was flagged Recently Cancelled and no longer appears from the 2026-02 edition.

  9. Left the queue AB P3129

    Swan Hills Data Load leaves the queue, 932 MW

    P3129 was flagged Recently Cancelled and no longer appears from the 2026-02 edition.

  10. Policy BC

    BC Hydro issues the 2026 Call for Demand for Emerging Industries Request for Applications.

    Eligibility 10–145 MW; bid security $25,000/MW by letter of credit; minimum 10% price premium on demand and energy charges under the applicable electric tariff; minimum…

January 2026 9 entries
  1. Policy NB

    Effective date of NB Power's most recent Interconnection Study Statistics posting (three PDFs: Feasibility Reviews Completed, System Impact Studies, Summary Statistics; file metadata shows production on 2026-05-21).

  2. Policy BC

    B.C. Reg. 8/2026 (O.C. 25/2026), Data Centre Facility and Hydrogen Production Facility Power Supply Regulation, deposited and effective.

  3. Policy BC

    Province and BC Hydro announce the launch of the competitive selection process for AI and data centres, up to 400 MW over the first two years, applications open, successful applicants to be notified September 2026.

  4. Announcement AB

    Synapse Data Center Inc. announces 1,000 MW at Olds, AB

    Synapse Olds Data Centre

  5. Policy NS

    Nova Scotia sets an all-time record system peak of 2,459 MW, exceeding the prior record of 2,455 MW (4 Feb 2023).

    Establishes the scale against which a 75-325 MW load must be judged.

  6. Policy BC

    Results of BC Hydro's 2025 Call for Power announced: 14 proposals (13 wind, 1 solar) totalling over 9,100 GWh/yr and more than 3,000 MW, individual projects 63–496 MW, all with minimum 25% First Nations equity, ~$6B private investment.

  7. Policy AB

    Government of Canada launches a call for proposals for sovereign large-scale AI data centres above 100 MW, with successful proponents eligible to enter an MOU with the federal government.

  8. Policy NS

    NSEB Renewable to Retail Implementation Hearing, regulatory work to make the retail supply market operational.

    Despite it, as of 5 Jun 2026 the RtR market still has one participant (Renewall Energy Inc.) and no pending applicants.

  9. Joined the queue AB P3110

    Mihta Askiy Data Load joins the Alberta queue at 300 MW

    P3110 appears on AESO's connection list for the first time in the 2026-01 edition.

December 2025 11 entries
  1. Policy AB

    Royal assent to Bill 8, Utilities Statutes Amendment Act, 2025, on December 11, 2025.

    The act is intended to encourage data centres to bring their own generation to support their connection to Alberta's electricity grid, and to align with a cost-causation framework for transmission under which data centres, not Alberta ratepayers, pay for necessary transmission upgrades.

  2. Policy ON

    Bill 40 receives royal assent as S.O. 2025 c.22 (first reading June 3, second November 17, third December 8, 2025).

    Schedule 1 comes into force on royal assent, so Electricity Act s.28.1 is law from this date.

  3. Policy BC

    Regulatory package under Bill 31 takes effect: BC Hydro electric tariff amendments to facilitate industrial connections, a ministerial order exempting BC Hydro from the CPCN requirement for the North Coast Transmission Line, and measures that provide clarity regarding security provisions required to access the line.

  4. Announcement MB

    Jet.AI Inc. / Consensus Core Technologies Inc. announces 100 MW at North of Île-des-Chênes, RM of Ritchot, Manitoba

    Convergence Compute Midwestern Canadian Data-Center Campus (Île-des-Chênes)

  5. Joined the queue AB P3146

    Hanna MPC Data Load joins the Alberta queue at 800 MW

    P3146 appears on AESO's connection list for the first time in the 2025-12 edition.

  6. Joined the queue AB P3156

    High Plains East Industrial Park joins the Alberta queue at 300 MW

    P3156 appears on AESO's connection list for the first time in the 2025-12 edition.

  7. Given a date AB P2952

    North Calgary One Data Centre MPC Load is given a grid date of 2028-06-07

    AESO issued an in-service date for P2952 at 75 MW. Only a minority of the queue carries one.

  8. Slipped AB P2953

    North Calgary Two Data Centre MPC Load slips 18 months, to 2028-09-13

    The in-service date for P2953 moved from 2027-03-26 to 2028-09-13 between the 2025-11 and 2025-12 editions.

  9. Slipped AB P3141

    Opal Data Load slips 2 months, to 2027-02-11

    The in-service date for P3141 moved from 2026-12-08 to 2027-02-11 between the 2025-11 and 2025-12 editions.

  10. Announcement AB

    Technologies New Energy announces 240 MW at Multiple sites: Olds, Calgary, Edmonton and Bonnyville, AB

    Technologies New Energy & Data District Data Centres (Phase 1)

  11. Announcement ON

    Microsoft announces at Vaughan

    Microsoft YTO11 / YTO12 Data Centre Campus

November 2025 12 entries
  1. Policy NS

    NSEB approves the NS-NB Reliability Intertie (second 345 kV AC line to New Brunswick), filed 10 Apr 2025 by Wasoqonatl Transmission Incorporated.

    Anticipated in service Q4 2028. Roughly 3.5 years filing to energization for a major transmission asset.

  2. Policy NB

    NB Power chief commercial officer Brad Coady sets out the utility's commercial position on large loads: it will seek agreements requiring data centres to shut down or run solely on their own on-site generation or storage during peak demand.

  3. Policy MB

    Reported from Manitoba Hydro's responses to Public Utilities Board questions: 13 data centre connection requests are under various stages of review, with at least one service contract signed; Manitoba Hydro treats further detail as commercially sensitive.

  4. Dates withdrawn AB

    AESO withdraws in-service dates across the queue: 18,052 MW dated falls to 1,444 MW

    23 projects moved from Active to ISD Under Review in a single edition, a 92% fall in dated capacity. The queue grew from 32 entries to 38 in the same month.

  5. Joined the queue AB P3151

    GLDC Load Phase 1.2 joins the Alberta queue at 830 MW

    P3151 appears on AESO's connection list for the first time in the 2025-11 edition.

  6. Joined the queue AB P3153

    Alsike Energy Park MPC Data Load joins the Alberta queue at 280 MW

    P3153 appears on AESO's connection list for the first time in the 2025-11 edition.

  7. Joined the queue AB P3154

    Lone Pine Energy Park MPC Data Load joins the Alberta queue at 280 MW

    P3154 appears on AESO's connection list for the first time in the 2025-11 edition.

  8. Joined the queue AB P3155

    Myers Energy Park MPC Data Load joins the Alberta queue at 280 MW

    P3155 appears on AESO's connection list for the first time in the 2025-11 edition.

  9. Joined the queue AB P3152

    Keephills Data Centre Phase 1.2 joins the Alberta queue at 180 MW

    P3152 appears on AESO's connection list for the first time in the 2025-11 edition.

  10. Joined the queue AB P3141

    Opal Data Load joins the Alberta queue at 0 MW

    P3141 appears on AESO's connection list for the first time in the 2025-11 edition.

  11. Given a date AB P2936

    GLDC Load Phase 1.1 is given a grid date of 2027-05-01

    AESO issued an in-service date for P2936 at 970 MW. Only a minority of the queue carries one.

  12. Slipped AB P3126

    Sollair Load slips 16 months, to 2028-01-01

    The in-service date for P3126 moved from 2026-09-01 to 2028-01-01 between the 2025-10 and 2025-11 editions.

October 2025 6 entries
  1. Announcement NB

    Beacon Data Centers / VoltaGrid announces 390 MW at Lorneville, Saint John, New Brunswick

    Saint John AI Data Centre (Spruce Lake Industrial Park / Lorneville)

  2. Announcement AB

    Havenz Smart Communities announces at Blindman Industrial Park, Red Deer County, AB (near Blackfalds)

    Blindman Industrial Park AI Data Centre

  3. Joined the queue AB P3137

    Sheerness Data MPC Load joins the Alberta queue at 800 MW

    P3137 appears on AESO's connection list for the first time in the 2025-10 edition. Filed in stages: 400 MW at EN1, 400 MW at EN2.

  4. Joined the queue AB P3136

    Sundance Data MPC Load joins the Alberta queue at 401 MW

    P3136 appears on AESO's connection list for the first time in the 2025-10 edition.

  5. Joined the queue AB P3126

    Sollair Load joins the Alberta queue at 74 MW

    P3126 appears on AESO's connection list for the first time in the 2025-10 edition. Filed in stages: 5 MW at EN1, 70 MW at EN2.

  6. Slipped AB P3102

    Goldfinch Technology Park MPC Load slips 12 months, to 2030-01-01

    The in-service date for P3102 moved from 2029-01-01 to 2030-01-01 between the 2025-09 and 2025-10 editions.

September 2025 5 entries
  1. Announcement ON

    BUZZ High Performance Computing Inc. announces 7 MW at 15 City View Drive, Etobicoke, Toronto, ON

    BUZZ HPC Toronto Site (15 City View Drive, Etobicoke)

  2. Joined the queue AB P3129

    Swan Hills Data Load joins the Alberta queue at 932 MW

    P3129 appears on AESO's connection list for the first time in the 2025-09 edition. Filed in stages: 466 MW at EN1, 233 MW at EN2, 233 MW at EN3.

  3. Slipped AB P3109

    Newell Data Center MPC Load slips 24 months, to 2029-12-01

    The in-service date for P3109 moved from 2027-12-01 to 2029-12-01 between the 2025-08 and 2025-09 editions.

  4. Policy MB

    M.R.

    68/2025 comes into force on September 1, 2025. From this date, related projects are aggregated where Manitoba Hydro is satisfied they are in substance a single project and five or more megawatts are requested in relation to the projects after August 31, 2025, and the corporation must deny a request for service by a customer if the proposed use of the power is directly or indirectly related to mining a cryptocurrency.

  5. Policy MB

    Manitoba Hydro's public 'Apply for large power supply' page reflects the new regime: applications for a supply of power greater than 5 megawatts go to LocateInManitoba@hydro.mb.ca, and once a complete application is submitted, Manitoba Hydro evaluates the request to determine if it is eligible, reasonably feasible, and subject to a priority designation, in accordance with The Manitoba Hydro Act and the Requests for Service Regulation.

August 2025 9 entries
  1. Policy MB

    Requests for Service Regulation, M.R. 68/2025, registered under The Manitoba Hydro Act.

  2. Announcement ON

    Prologis announces 40 MW at Northwest corner of Tenth Line West and Argentia Road, Mississauga (Meadowvale Business Park)

    Prologis Meadowvale Business Park Data Centre

  3. Announcement ON

    QScale announces at Wilmot Township (near Nafziger Rd / Bleams Rd), Waterloo Region

    QScale Wilmot Township Data Centre (proposed)

  4. Joined the queue AB P3124

    Evarts Data Load joins the Alberta queue at 1,000 MW

    P3124 appears on AESO's connection list for the first time in the 2025-08 edition.

  5. Joined the queue AB P3116

    Rocky View Data Center MPC Load joins the Alberta queue at 800 MW

    P3116 appears on AESO's connection list for the first time in the 2025-08 edition. Filed in stages: 400 MW at EN1, 400 MW at EN2.

  6. Joined the queue AB P3114

    Banshee Data MPC Load joins the Alberta queue at 150 MW

    P3114 appears on AESO's connection list for the first time in the 2025-08 edition.

  7. Slipped AB P3101

    Carstairs Technology Park MPC Load slips 8 months, to 2029-01-01

    The in-service date for P3101 moved from 2028-05-01 to 2029-01-01 between the 2025-07 and 2025-08 editions.

  8. Slipped AB P3102

    Goldfinch Technology Park MPC Load slips 8 months, to 2029-01-01

    The in-service date for P3102 moved from 2028-05-01 to 2029-01-01 between the 2025-07 and 2025-08 editions.

  9. Policy PE

    Maritime Electric files a supplemental capacity filing for two 50 MW combustion turbines, citing electrification and data centre development among the drivers.

July 2025 4 entries
  1. Announcement ON

    Ascent Corp / Related Digital / TowerBrook Capital Partners announces 60 MW at 17 Vondrau St, Cambridge

    Ascent/Related Digital Cambridge Data Centre (17 Vondrau St, TOR1 campus)

  2. Announcement AB

    Capital Power announces 1,500 MW at Leduc County, AB (Genesee Generating Station, ~71 km southwest of Edmonton)

    Genesee Data Centre Project

  3. Announcement AB

    Not identified announces at Rocky View County, AB — SW-09-23-27W04, SE-09-23-27W04 and NE-09-23-27W04, ~194 hectares (479 acres) along Township Road 232, ~10 km east of Calgary city limits and ~2 km southwest of the Hamlet of Langdon, 1.6 km west of Highway 797

    Wild Rose Power Hub (proposed, Area Structure Plan under review)

  4. Left the queue AB P2919

    Forestwood Technology Park MPC Load leaves the queue, 200 MW

    P2919 was flagged Recently Cancelled and no longer appears from the 2025-07 edition.

June 2025 7 entries
  1. Announcement AB

    Crusoe announces 280 MW at Red Deer County, AB (Myers Energy Park)

    Crusoe AI Data Centre - Myers Energy Park

  2. Announcement AB

    Crusoe announces 280 MW at Brazeau County, AB (Alsike, near Drayton Valley)

    Crusoe AI Data Centre - Alsike Energy Park

  3. Announcement AB

    Crusoe announces 170 MW at Rocky View County, AB (near Crossfield)

    Crusoe AI Data Centre - Crossfield Energy Park

  4. Announcement AB

    Beacon AI Centers / Indus Power Generation LP announces 1,200 MW at Rocky View County, AB — Section 11, Township 23, Range 28, W4M; ~3 km east of Calgary, ~2 km northwest of the Hamlet of Indus

    Beacon AI Hub — Indus (with Indus Project Thermal Power Plant)

  5. Slipped AB P3078

    Calgary A.I. Centre Load slips 12 months, to 2028-01-15

    The in-service date for P3078 moved from 2027-01-15 to 2028-01-15 between the 2025-05 and 2025-06 editions.

  6. Slipped AB P3075

    Balzac Area Load slips 23 months, to 2026-12-01

    The in-service date for P3075 moved from 2025-01-01 to 2026-12-01 between the 2025-05 and 2025-06 editions.

  7. Announcement SK

    Carpere Valley Development Corporation announces 150 MW at Former Valley View Centre site, south of Moose Jaw, Saskatchewan

    Carpere Valley / Aztec AI Health — Valley View (Moose Jaw)

May 2025 14 entries
  1. Announcement BC

    Bell Canada, with Groq announces 7 MW at Kamloops, BC

    Bell AI Fabric Kamloops

  2. Announcement BC

    Bell Canada announces 7 MW at Merritt, BC

    Bell AI Fabric Merritt (with Buzz HPC)

  3. Announcement BC

    Bell Canada announces 26 MW at Kamloops, BC

    Bell AI Fabric Kamloops -- Thompson Rivers University site

  4. Announcement BC

    Bell Canada announces 400 MW at British Columbia (location undisclosed)

    Bell AI Fabric -- two additional undisclosed BC sites

  5. Announcement QC

    Dogecoin Mining Technologies Corp. announces 11 MW at Quebec, Canada (exact site/town not disclosed in public sources found)

    DMTC / Hyper Bit Quebec crypto facility

  6. Joined the queue AB P3108

    Wild Rose Power Hub Load joins the Alberta queue at 1,300 MW

    P3108 appears on AESO's connection list for the first time in the 2025-05 edition. Filed in stages: 300 MW at EN1, 1,000 MW at EN2.

  7. Joined the queue AB P3109

    Newell Data Center MPC Load joins the Alberta queue at 1,200 MW

    P3109 appears on AESO's connection list for the first time in the 2025-05 edition. Filed in stages: 400 MW at EN1, 400 MW at EN2, 400 MW at EN3.

  8. Joined the queue AB P3112

    North Calgary Three Data Centre MPC Load joins the Alberta queue at 450 MW

    P3112 appears on AESO's connection list for the first time in the 2025-05 edition.

  9. Joined the queue AB P3101

    Carstairs Technology Park MPC Load joins the Alberta queue at 400 MW

    P3101 appears on AESO's connection list for the first time in the 2025-05 edition.

  10. Joined the queue AB P3102

    Goldfinch Technology Park MPC Load joins the Alberta queue at 400 MW

    P3102 appears on AESO's connection list for the first time in the 2025-05 edition.

  11. Joined the queue AB P3106

    Alberta South A.I. Load joins the Alberta queue at 400 MW

    P3106 appears on AESO's connection list for the first time in the 2025-05 edition. Filed in stages: 200 MW at EN1, 200 MW at EN2.

  12. Joined the queue AB P3107

    Chestermere Enterprise A.I. Load joins the Alberta queue at 400 MW

    P3107 appears on AESO's connection list for the first time in the 2025-05 edition. Filed in stages: 200 MW at EN1, 200 MW at EN2.

  13. Joined the queue AB P3075

    Balzac Area Load joins the Alberta queue at 45 MW

    P3075 appears on AESO's connection list for the first time in the 2025-05 edition. Filed in stages: 15 MW at EN1, 15 MW at EN2, 15 MW at EN3.

  14. Left the queue AB P2883

    Stack Point Trotter Load leaves the queue, 55 MW

    P2883 was flagged Recently Cancelled and no longer appears from the 2025-05 edition.

April 2025 2 entries
  1. Announcement AB

    Completely unconfirmed -- AESO project name does not indicate an operator, and no press coverage was found announces 300 MW at 19-Peace River planning area, AB (exact site not disclosed by AESO)

    Mihta Askiy Data Load (AESO filing)

  2. Announcement AB

    Kineticor Asset Management announces at Rocky View County, AB (northeast quadrant, near Delacour/Balzac area)

    Rocky View County Data Centre / Technology Park (Kineticor ASP)

March 2025 6 entries
  1. Announcement ON

    55H / CORE Data Centres announces 20 MW at 55 Hereford St, Brampton

    55H High-Density Colocation Data Centre

  2. Joined the queue AB P3095

    Keephills Data Centre Phase 2 joins the Alberta queue at 466 MW

    P3095 appears on AESO's connection list for the first time in the 2025-03 edition.

  3. Joined the queue AB P3083

    Keephills Data Centre Phase 1.1 joins the Alberta queue at 395 MW

    P3083 appears on AESO's connection list for the first time in the 2025-03 edition.

  4. Joined the queue AB P3079

    Captus Load joins the Alberta queue at 100 MW

    P3079 appears on AESO's connection list for the first time in the 2025-03 edition.

  5. Slipped AB P2952

    North Calgary One Data Centre MPC Load slips 4 months, to 2027-03-26

    The in-service date for P2952 moved from 2026-12-01 to 2027-03-26 between the 2025-02 and 2025-03 editions.

  6. Slipped AB P2953

    North Calgary Two Data Centre MPC Load slips 4 months, to 2027-03-26

    The in-service date for P2953 moved from 2026-12-01 to 2027-03-26 between the 2025-02 and 2025-03 editions.

February 2025 7 entries
  1. Announcement QC

    Vantage Data Centers announces 86 MW at 2675 Boulevard du Parc Technologique, Quebec City, QC

    Vantage Quebec City Campus (QC2, incl. QC21/QC23/QC24)

  2. Announcement AB

    Beacon Data Centres announces 400 MW at Chestermere, AB

    Beacon AI Data Centre Hub - Chestermere

  3. Announcement AB

    Bitdeer Technologies Group announces 101 MW at Fox Creek, AB

    Bitdeer Fox Creek Facility

  4. Joined the queue AB P3066

    Leedale Data Load joins the Alberta queue at 1,864 MW

    P3066 appears on AESO's connection list for the first time in the 2025-02 edition.

  5. Joined the queue AB P3077

    Calgary Enterprise A.I. Load joins the Alberta queue at 200 MW

    P3077 appears on AESO's connection list for the first time in the 2025-02 edition. Filed in stages: 100 MW at EN1, 100 MW at EN2.

  6. Joined the queue AB P3078

    Calgary A.I. Centre Load joins the Alberta queue at 150 MW

    P3078 appears on AESO's connection list for the first time in the 2025-02 edition. Filed in stages: 50 MW at EN1, 50 MW at EN2, 50 MW at EN3.

  7. Left the queue AB P2615

    High Plains Balzac Load leaves the queue, 75 MW

    P2615 was flagged Recently Cancelled and no longer appears from the 2025-02 edition.

January 2025 3 entries
  1. Announcement ON

    Yondr Group announces 27 MW at Toronto (Don Valley North)

    Yondr Toronto Data Center (TOR1)

  2. Policy YT

    Coverage confirms large industrial customers require dedicated PPAs and 20-25 year infrastructure commitments.

  3. Announcement ON

    Slate Asset Management announces 400 MW at Hamilton waterfront, former Stelco steelworks lands

    Steelport AI Data Centre Campus (former Stelco lands)

How this is built

Every item is derived from a primary source rather than written: queue events from diffing consecutive AESO editions, policy events from verified jurisdiction research, project events from announcement dates on sourced rows.

Covering 2025-01-01 to 2026-08-18.

Alberta · AR 117/2026 · current as of 9 June 2026

Alberta now puts data centres that bring their own generation to the front of the queue.

The Data Centre Regulation, AR 117/2026, replaced the interim 1,200 MW cap. A project that brings its own generation is processed first; everyone else is subject to conditions AESO sets. The binding constraint has moved off the wires and onto plant, and AESO calls the route bring your own generation.

The clauses that decide it

Binding law

s.2 A large data centre is 75 MW or more, and the line can move down
At or above 75 MW of maximum demand a project is a "large data centre". That figure is a default rather than a floor: s.2(2) lets AESO set a lower threshold on reliability or adequacy grounds, so sizing just under it is not a durable way out of the regime.
s.6 Tethered requests are processed first
AESO must prioritise processing a request from a tethered data centre over one from a large data centre that is not tethered. This is the regulation's actual operating mechanism: untethered load is deprioritised, not prohibited.
s.5 Being tethered means bringing incremental generation
AESO may designate a data centre tethered to generating units capable of supplying the transmission system at a rate at least equal to its maximum demand. The supply offsets into the common pool rather than being wired privately to the load, but it must be incremental: a proposed unit must be new, and an existing unit qualifies only where its service is being modified upward or it has been declared under the relevant provisions.
s.7 Financing and water licences can gate service
AESO may set criteria covering site control, municipal zoning approvals, financing, and the issuance of permits or water licences, and meeting them is a condition of service being provided.
s.9(5) Bridged supply runs three years at the outside
Where AESO grants bridged service, grid energy taken before the tethered generation runs, it may run for a maximum of three years from when it is first provided. Bridging is discretionary throughout: s.9(1) says "may provide", and s.9(2) gates it on AUC approval of the tethered units.
s.10 Curtailment falls on data centres first, in two stages
On a determination of inadequate supply, bridged data centres reduce demand before all other market participants. Separately, where mandatory load shedding is required, every large data centre reduces before the rest of the market. The two limbs have different triggers and a non-bridged site is exposed only to the second.
s.3 Adjacent sites can be treated as one, if they are related
AESO may aggregate two or more data centres into one where they are physically or operationally integrated and on the same or adjacent parcels, AND a common person or affiliate is receiving or requesting service for them. Both limbs are required, so unrelated neighbours are not captured.
s.12 The regime is reviewed by 2030 and expires in 2035
The regulation must be reviewed on or before 31 May 2030 and expires on 31 May 2035. Anything underwritten against it should be underwritten against that clock.

Proposed, not yet law

AESO published the Phase 2A design on 26 June 2026 for rollout from August 2026. Intake opens immediately on release of the process material and runs six weeks, with no grace for late applications. These mechanics are a proposal and are marked as such because most summaries report them as settled:

  • An intake window of six weeks, opening on rollout. AESO says later cycles will align with cluster studies but has published no cadence and no date for a second intake.
  • A commitment payment of C$15,000 per MW of requested service, refunded on contract execution.
  • A system-wide bridging pool of 1,600 MW, released in tranches against milestones.
  • Tethered generation limited to gas-fired plant in the first cycle, described as provisional and reviewable.

What it means for a build

Tethering buys processing priority and, at AESO's discretion, up to three years of bridged supply while the plant is built. Going without it means waiting behind everyone who did, on conditions AESO sets. Both roads end at the same place: securing generating equipment against a date, in a market where new heavy-duty OEM slots are being signed into 2031 and even smaller turbines run 18 to 36 months.

Regulation text read directly from Alberta King's Printer, current as of 9 June 2026. Phase 2A mechanics from AESO's published Large Load Integration materials. Where a secondary summary and the regulation disagreed, the regulation was used. This section was corrected on 2026-08-02 after an independent audit found it overstated the regulation as a prohibition; see the changelog.