McCord Investments

Power and industrial equipment sourcing

Send a requirement Requirement

Map / Provinces / MB

Manitoba

Manitoba Hydro; Public Utilities Board regulates rates

Closed to unsolicited large load: government now picks which projects get power, and it has already said no to at least one data centre.

6MW

announced in Manitoba, not yet operating

1 tracked projects

8MW

energized in Manitoba

1 with published capacity

Publishes nothing project level. No. Manitoba has nothing comparable to AESO's monthly Connection Project List. Manitoba Hydro publishes no project-level list of pending or approved large-load connections, no project IDs, no per-project MW, no requested in-service dates, no queue positions, and no aggregate MW total for the large-load pipeline.


The record

Operator detail
Manitoba Hydro is the connecting utility, confirmed, with an important correction: since 1 September 2025 it is no longer the sole approver. The Manitoba Hydro Act s.22 gives Manitoba Hydro exclusive authority to supply power in Manitoba (consolidation current to 30 July 2026, https://web2.gov.mb.ca/laws/statutes/ccsm/h190.php?lang=en).
Route to power
A 100+ MW data centre is a "large supply of power" (threshold 5 MW; two or more projects are aggregated where Manitoba Hydro is satisfied they are in substance a single project and 5+ MW is requested after 31 August 2025, M.R. 68/2025). The route today: 1. Application. Complete Manitoba Hydro's large power supply request form (legal entity, site, construction start, power factor, peak demand in MW, annual energy in GWh/yr, gas requirements, efficiency measures, employment and impact) and email it with supporting documents to LocateInManitoba@hydro.mb.ca. A request is only "made" once the customer has provided all information the corporation requires (M.R. 68/2025 s.2).
Typical timeline
No public application-to-energization figure exists for a 100+ MW load in Manitoba. Manitoba Hydro publishes only the study stages: Load Interconnection Evaluation Study 3-5 months, then customer-funded Detailed Engineering Study 6-8 months (roughly 9-13 months of study before a construction agreement), after which "service design and installation" timing "varies based on customer requirements and environmental licen…
Binding constraint
Discretionary ministerial allocation plus a hard capacity wall, not a numeric cap. There is no Manitoba equivalent of Alberta's 1,200 MW interim cap and no Quebec-style block allocation call for data centre load. The binding constraints, in order: 1. Ministerial priority gate (in force 1 Sept 2025). Every >5 MW request is ranked low/medium/high by the Minister; low-priority requests are deferred behind all medium and high requests and served only if capacity would not be impaired; no appeal. M.R. 68/2025 ss.7-13. This is a political allocation decision, not a technical one, and no allocated volume is published.
Behind the fence
Legally possible, but it does not buy you a way around the province, and Manitoba has just demonstrated that. What is allowed. Manitoba Hydro's s.22 exclusive authority is an authority to supply power to persons in Manitoba, subject to exceptions in the Act and regulations; it forecloses buying power from a third-party IPP, but a facility generating for its own use behind its own fence is not being "supplied" by anyone.
Interconnection
Manitoba banned new crypto mining connections in 2022. Bill 28, The Manitoba Hydro Amendment Act (first reading 2025-03-06), ends first-come-first-served for large grid connections and lets the Finance Minister direct Manitoba Hydro on whether a 'large supply of power' request should be prioritized. In practice this has already been used: the government rejected a proposed large-scale data centre at Île-des-Chênes (Verified via the corresponding project row and a direct live fetch of the underlying Jet.AI press release).
Tariff
No dedicated data centre tariff exists; the binding constraint is political approval under Bill 28, not price. Newest confirmed source dates to November 2025; verify no further Bill 28 regulations have since been enacted.
Years to grid power
n/a, government approval is now a precondition and is being exercised to reject projects rather than queue them
Years behind the fence
n/a, no published BTF pathway
Basis for those years
Manitoba Hydro's own 2025 Integrated Resource Plan Road Map states new dependable supply is needed within five years and does not factor data centres into future resource plans; combined with Bill 28's feasibility-denial power and the Île-des-Chênes rejection, no basis exists for a connection-time figure.

Dated events

Tracked projects

Project Status Announced Energized Target online
Convergence Compute Midwestern Canadian Data-Center Campus (Île-des-Chênes) Not approved 100 MW Not stated Not stated
Equinix WI1 Winnipeg (formerly Bell MTS Data Centre) Operating 8 MW 8 MW Not stated
Bell AI Fabric Rosser (CentrePort) Construction 6 MW Not stated 2027

Announced capacity is what the proponent has stated. Energized capacity is what is drawing. They are different figures and are never summed. How the figures reconcile.

Sources

Known gaps. 1. End-to-end timeline is not published. Manitoba Hydro publishes study durations (3-5 months, then 6-8 months) but no application-to-energization figure for a 100+ MW load, and construction duration is stated only as varying. The ministerial priority designation has no statutory deadline ("as soon as practicable"). Found no credible public report of an actual elapsed time for any Manitoba large load. 2. No pipeline volume is public. Statute re-verification, 2026-08-16. The Manitoba Hydro Act was amended twice in 2026 (S.M. 2026, c. 17 and c. 32, Part 1), which raised the question of whether the binding-constraint text on this card, which rests on s.49.2 and M.R. 68/2025, still holds. The official consolidation was read in full on 2026-08-16. It states it is current from 1 April 2026 to 13 August 2026 and is the most current version available. Section 49.2 is present and unchanged in substance: the corporation must deny a request for service prescribed as ineligible, must deny a request for a large supply of power where supply is not reasonably feasible or prescribed requirements are unmet, its determination is final, and the minister may direct priority service in the public interest. Its source note reads S.M. 2025, c. 25, s. 4, and no S.M. 2026 amendment note appears on the section or anywhere in the consolidation. Neither 2026 amendment touches the large-load or requests-for-service regime. No dated event is added and the constraint text is left as written; only the verification date moves. The CanLII consolidation was blocked by a CAPTCHA and was not used.


Record updated 2026-08-16. Sources reviewed 2026-08-16. Corrections: sam@mccordinvestments.com

External document

This is hosted by the publisher, not by McCord, and your browser may download it rather than open it in a tab.

Open the document