Bell AI Fabric Rosser (CentrePort)
Bell Canada / 400 Goldenrod Drive, Rosser (CentrePort Canada), RM of Rosser, Manitoba
Construction
6 MW
announced
0 MW
energized
None of it is drawing power yet.
- 2026-04-29 Announced
- 2027 Developer target stated by the developer, not a filed date
- Power path
- Grid
- Generation tech
- Not stated
- Utility
- Manitoba Hydro
- Queue reference
- Not stated
- Target online
- 2027
- Announced
- 2026-04-29
- Verification
- multiple
- Coordinate
- 49.9833, -97.3667 (town)
Getting power in Manitoba
Closed to unsolicited large load: government now picks which projects get power, and it has already said no to at least one data centre.
The full Manitoba record, with the route to power, the binding constraint and every dated policy event.
Sources
- AI data centre going into shuttered protein plant just outside Winnipeg
- AI data centre going into shuttered protein plant just outside Winnipeg | CBC News
- Bell Canada to turn Winnipeg food processing plant into AI data center
Adaptive reuse of former Merit Functional Foods pea-protein plant. Three building/development permits filed with the South Interlake Planning District (totaling $31.5M+ construction: wall modifications, concrete pads for generators/chillers/transformers) plus multiple independent press reports of physical retrofit work -- this filing evidence is why 'construction' is justified per hard rules. Target online late 2026/early 2027.
Other tracked projects in Manitoba
- Convergence Compute Midwestern Canadian Data-Center Campus (Île-des-Chênes) Jet.AI Inc. / Consensus Core Technologies Inc. (joint venture: Convergence Compute) · 100 MW · Not approved
- Equinix WI1 Winnipeg (formerly Bell MTS Data Centre) Equinix · 8 MW · Operating
Last verified 2026-08-01. Corrections: sam@mccordinvestments.com