New Brunswick

NB Power; New Brunswick Energy and Utilities Board

Open but non-committal: the utility says it can handle a specific 190 MW request but wants flexible, interruptible load, not firm baseload commitments.

390MW

announced in New Brunswick, not yet operating

1 tracked projects

0MW

energized in New Brunswick

0 with published capacity

Publishes a project-level list. Yes, but it is Not comparable to AESO's Connection Project List, and the differences are the ones that matter. NB Power posts a page called 'Interconnection Study Statistics' (linked from the TSO Data page) carrying three PDFs. The most recent vintage is dated 2026-01-31 (file metadata shows it was produced 2026-05-21). Verified 2026-08-02. The published tables carry application date, completion date, county, MW and project type, and mark load separately from wind, solar, battery and generation. They do not name the applicant or the site, so a reader can see that a 200 MW load in Saint John was reviewed but not who is behind it. It is a record of studies completed, not a queue of projects waiting.


The record

Operator detail
NB Power (New Brunswick Power Corporation), confirmed. There is no independent system operator; the New Brunswick System Operator was folded back into NB Power in 2013. Connection approval sits with "NB Power – System Operation" (Nbp-so), acting as Transmission Provider under the NB Open Access Transmission Tariff (Oatt, current version effective 2023-01-01) and the Electricity Business Rules.
Route to power
A 100+ MW data centre follows two parallel tracks, both run by NB Power. There is no separate large-load tariff and no data-centre-specific process. Track 1, Connection assessment (Electricity Business Rules, Appendix B "Connection Assessment Procedure", Version 02, effective 2023-12-31). Named stages, in order: 1. Project definition / design by the applicant. 2. Feasibility review, mandatory. Form B-01 "Application for Feasibility Review for Generation and/or Loads". Non-refundable application fee: $5,000 plus taxes for projects at this scale (also $5,000 for point-to-point service requests over 100 MW; zero for small projects). Includes a "determination of need".
Typical timeline
No end-to-end application-to-energization timeline is published by NB Power or the province. What IS public: Rule-book targets (Appendix B Part 5, all explicitly non-binding, "the Transmission Provider's obligation is general diligence rather than specific timelines"): Feasibility Review "typically expected to be complete within two weeks of a completed application"; System Impact Study "typically ...
Binding constraint
There is NO formal cap, NO moratorium and NO block-allocation process for data centre load in New Brunswick as of 2026-08-01. Nothing resembling Alberta's 1,200 MW interim cap or Quebec's allocation calls exists. That absence is itself the finding, and it has been tested twice in 2026: - 2026-06-11/17: Green MLA Megan Mitton moved a resolution for an immediate moratorium on big data centres. The government refused; when Mitton sought unanimous consent to extend the sitting to force a vote, Liberal members shouted "no" and the House adjourned without voting.
Behind the fence
Yes, and in New Brunswick self-supply is currently the faster and legally cleaner half of a hybrid project. The Lorneville proposal is built on exactly this: of ~390 MW total, ~190 MW comes from an on-site VoltaGrid natural gas plant and ~190–200 MW from the NB Power grid. Beacon AI's Joseph Shovlin told a public meeting the project has a fallback if NB Power will not supply: "This gentleman here will provide the power and we'll be totally disconnected." The statutory position (Electricity Act, S.n.b.
Interconnection
No formal large-load queue or moratorium is published. The clearest live test case is the proposed Lorneville (Saint John) data centre (VoltaGrid/Beacon AI Centers, Verified as an existing, well-sourced project row in this dataset) seeking 380-390 MW total: ~190-200 MW behind-the-fence gas generation plus a grid request. NB Power has stated it is not alarmed by the request but wants flexibility/interruptibility.
Tariff
No data centre-specific tariff exists. The pending Rate Design Application would end the declining-block discount for new large industrial customers if approved; approval status not confirmed.
Years to grid power
n/a, no end-to-end figure published; feasibility review alone has run a median of 4.2 months
Years behind the fence
2-4
Basis for those years
Grid figure: NB Power publishes no end-to-end connection timeline, confirmed 2026-08-02 against its own connection page, where the only load-facing artefact is form B-01, the Application for Feasibility Review. What it does publish is the completed reviews. In the 31 January 2026 edition, 15 completed reviews are marked Load, totalling 925 MW, with a median application-to-completion time of 127 days, 4.2 months, across a 46 to 286 day range. The longest is the most recent large one: a 200 MW load in Saint John took 286 days. That is the first study stage only, not time to power, and nothing downstream of it is published. BTF figure: 2-4 years, from the Lorneville case, which remains at the request stage.

Dated events

Tracked projects

Project Status Announced Energized Target online
Saint John AI Data Centre (Spruce Lake Industrial Park / Lorneville) Announced 390 MW Not stated 2028

Announced capacity is what the proponent has stated. Energized capacity is what is drawing. They are different figures and are never summed. How the figures reconcile.

Sources

Known gaps. Things Could not establish from public sources, stated plainly. 1. Application-to-energization. No New Brunswick source, NB Power, NBEUB or government, publishes an end-to-end timeline for a large load. I can give NB Power's own study-stage averages (401 / 112 / 299 days for feasibility, SIS and facilities studies in Q4 2025) and one real feasibility-stage datapoint (286 days for the 200 MW Saint John load), but the interval from connection agreement to energized service is unknown.


Record updated 2026-08-01. Sources reviewed 2026-08-02. Corrections: sam@mccordinvestments.com