Bell AI Fabric — RM of Sherwood

Bell Canada (Bell AI Fabric) / Rural Municipality of Sherwood No. 159, near Regina, Saskatchewan

Construction

300 MW

announced

0 MW

energized

None of it is drawing power yet.

  1. 2026-03-16 Announced
  2. 2027-H1 Developer target stated by the developer, not a filed date

Power path
Hybrid
Generation tech
grid (SaskPower transmission) plus behind-the-fence natural gas turbines for peak/backup
Utility
SaskPower
Queue reference
Not stated
Target online
2027-H1
Announced
2026-03-16
Verification
multiple
Coordinate
50.4452, -104.6189 (region)

Getting power in Saskatchewan

Open and courting, but riding on coal-refurbishment and nuclear plans that are not yet built.

The full Saskatchewan record, with the route to power, the binding constraint and every dated policy event.

Sources

The best-evidenced construction status in this dataset. The federal Impact Assessment Agency of Canada record states the project could not be designated for review because the physical activity had substantially begun, corroborated by CTV’s groundbreaking report and Bird Construction’s selection as contractor. The 300 MW figure matches the IAAC record. Phase 1 targets 200 MW of transmission by the end of 2026, Phase 2 a further 100 MW by the end of 2027.

Other tracked projects in Saskatchewan


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com

External document

This is hosted by the publisher, not by McCord, and your browser may download it rather than open it in a tab.

Open the document