UnitedCorp Beauharnois data centre / greenhouse project

UnitedCorp / Beauharnois, QC

Announced

40 MW

announced

0 MW

energized

None of it is drawing power yet.


Power path
Grid
Generation tech
crypto data centre domes + greenhouse photosynthetic lighting
Utility
Hydro-Quebec
Queue reference
Not stated
Target online
Not stated
Announced
2022-01-01
Verification
press
Coordinate
45.3168, -73.8745 (town)

Getting power in Quebec

Went from selling surplus hydro to data centres to actively pricing and gatekeeping them out.

The full Quebec record, with the route to power, the binding constraint and every dated policy event.

Sources

A single source from 2022, with no construction or permit evidence since. Likely stalled given Hydro-Québec’s 2023 moratorium on crypto-mining load.

Other tracked projects in Quebec


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com

External document

This is hosted by the publisher, not by McCord, and your browser may download it rather than open it in a tab.

Open the document