Map / QC
Verified 2026-08-01
OVHcloud BHS Campus
OVHcloud (OVH Group) / 40 Rue de l'Industrie, Beauharnois, QC
Operating
120 MW
announced
0 MW
energized
None of it is drawing power yet.
- Power path
- Grid
- Generation tech
- hyperscale colocation, hydro grid power
- Utility
- Hydro-Quebec
- Queue reference
- Not stated
- Target online
- Not stated
- Announced
- Not stated
- Verification
- press
- Coordinate
- 45.3168, -73.8745 (town)
Getting power in Quebec
Went from selling surplus hydro to data centres to actively pricing and gatekeeping them out.
The full Quebec record, with the route to power, the binding constraint and every dated policy event.
Sources
Built on a former Rio Tinto Alcan aluminum plant site adjacent to Hydro-Québec's Beauharnois generating station; well-established, independently reported since 2016 opening. 120MW figure is an aggregator (Baxtel) estimate, NOT an OVH-published figure -- flag MW as an estimate. Status 'operating' reasonable given the facility's long, independently-documented operating history.
Other tracked projects in Quebec
- QScale Q01 Campus QScale · 96 MW · Operating
- Vantage Quebec City Campus (QC2, incl. QC21/QC23/QC24) Vantage Data Centers · 86 MW · Construction
- Gatineau Data Hub (GDH) AVAIO Capital / Société immobilière ADAM · 50 MW · Not approved
- Bitfarms Sherbrooke – Bunker Keel Infrastructure (formerly Bitfarms Ltd.) · 48 MW · Operating
- UnitedCorp Beauharnois data centre / greenhouse project UnitedCorp · 40 MW · Announced
- eStruxture MTL-2 eStruxture Data Centers · 30 MW · Operating
- Vantage Montreal III (QC6) Vantage Data Centers · 30 MW · Operating
- Bitfarms Sherbrooke – Léger Keel Infrastructure (formerly Bitfarms Ltd.) · 30 MW · Operating
Last verified 2026-08-01. Corrections: sam@mccordinvestments.com