Vantage Montreal III

Vantage Data Centers / Baie-D’Urfé, QC

Operating

30 MW

announced

Not stated

energized

A single 30 MW building on an eight-acre site near Montréal-Trudeau airport, with its own 45 MW substation connected to Hydro-Québec. Vantage finished all phases in December 2025.


Power path
Grid
Setup
Hydro grid, own 45 MW substation
Utility
Hydro-Québec
Connection request
Not stated
Target online
Not stated
Announced
Not stated

Getting power in Quebec

Ministerial authorization. The Quebec record covers how projects get power there and what is changing.