Map / QC
Verified 2026-08-01
Bitfarms Sherbrooke – Bunker
Keel Infrastructure (formerly Bitfarms Ltd.) / Sherbrooke, QC
Operating
48 MW
announced
48 MW
energized
Fully energized against what was announced.
- Power path
- Grid
- Generation tech
- bitcoin mining, hydro grid power
- Utility
- Hydro-Quebec
- Queue reference
- Not stated
- Target online
- Not stated
- Announced
- Not stated
- Verification
- press
- Coordinate
- 45.4042, -71.8929 (town)
Getting power in Quebec
Went from selling surplus hydro to data centres to actively pricing and gatekeeping them out.
The full Quebec record, with the route to power, the binding constraint and every dated policy event.
Sources
One of three Bitfarms facilities on the Sherbrooke campus. The capacity figure comes from an industry aggregator rather than Bitfarms’ own filings.
Other tracked projects in Quebec
- OVHcloud BHS Campus OVHcloud (OVH Group) · 120 MW · Operating
- QScale Q01 Campus QScale · 96 MW · Operating
- Vantage Quebec City Campus (QC2, incl. QC21/QC23/QC24) Vantage Data Centers · 86 MW · Construction
- Gatineau Data Hub (GDH) AVAIO Capital / Société immobilière ADAM · 50 MW · Not approved
- UnitedCorp Beauharnois data centre / greenhouse project UnitedCorp · 40 MW · Announced
- eStruxture MTL-2 eStruxture Data Centers · 30 MW · Operating
- Vantage Montreal III (QC6) Vantage Data Centers · 30 MW · Operating
- Bitfarms Sherbrooke – Léger Keel Infrastructure (formerly Bitfarms Ltd.) · 30 MW · Operating
Last verified 2026-08-01. Corrections: sam@mccordinvestments.com