QScale Q01 Campus

QScale / Lévis, QC (2280 Albert-Dion St)

Operating

96 MW

announced

0 MW

energized

None of it is drawing power yet.

  1. 2020-01-01 Announced
  2. 2022 Developer target stated by the developer, not a filed date

Power path
Grid
Generation tech
colocation / HPC, hydro grid power, waste-heat reuse to adjacent greenhouse
Utility
Hydro-Quebec
Queue reference
Not stated
Target online
2022
Announced
2020-01-01
Verification
multiple
Coordinate
46.7382, -71.1809 (town)

Getting power in Quebec

Went from selling surplus hydro to data centres to actively pricing and gatekeeping them out.

The full Quebec record, with the route to power, the binding constraint and every dated policy event.

Sources

8-phase, CAD$867M build-out at a former paper mill site. Sources conflict 96MW (IT capacity) vs 142MW (total reserved HQ capacity) -- conservative IT figure used. Phase 1 complete end of 2022; DCD 'North American Data Center Project of the Year' 2023.

Other tracked projects in Quebec


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com