McCord Investments

Power and industrial equipment sourcing

Send a requirement

Home / Provinces / QC

Quebec

Hydro-Québec; Régie de l'énergie regulates tariffs

Route to power. Ministerial authorization. A project of 5 MW or more needs the government’s authorization, judged against seven published criteria. There is no published cap or queue. Entry is a decision, not a place in line.


How you connect

Hydro-Québec connects the project, but the government decides whether it gets power. You file Hydro-Québec’s form for projects of 5 MW and more with both Hydro-Québec and the economy ministry, which review it together. The answer is a conditional pre-authorization, a refusal, or a deferral that keeps the request open. While power is tight, projects are compared on the benefit they bring for each megawatt. The process is set out on the government’s authorization page.

Hydro-Québec publishes no connection time for a load this size.

Where there is room

Local transmission is the hard limit. Hydro-Québec’s December 2025 map of 13 industrial zones shows only five with 100 MW or more to spare without upgrades: Sept-Îles (150 MW), Chibougamau (120 MW), and Baie-Comeau, Beauharnois and Montréal-Est (100 MW each). Even there, a paid connection study sets the final scope, cost and schedule, and the spare capacity is not guaranteed.

What it costs

Hydro-Québec has filed a data centre rate of about 13 cents per kWh, roughly double the large-power rate, with a five-year phase-in for existing data centres. The Régie de l’énergie opened hearings on it on 1 October 2026, with more set for December; there is no decision yet. Large customers that use less than 60% of their reserved capacity over a year also face a charge, which some operators are challenging in court.

Bringing your own power

Allowed when it supplies only your own site. Since June 2025 the law says plainly that anyone may use the electricity they produce. Selling it to anyone else is still restricted.

Latest

The Parti Québécois won a minority government on 5 October 2026, so the next authorizations come from a new government.

What has happened

  1. Parti Québécois wins a minority government
  2. Hearings open on the proposed data centre rate; more follow in December
  3. Quebec publishes its energy resources plan to 2050
  4. Hydro-Québec updates its 5 MW project form, with a data centre appendix

Projects we track

Project Status Announced Energized Target online
QScale Q01 Campus Operating 142 MW Not stated 2022
Vantage Quebec City Campus Construction 86 MW Not stated 2027
Gatineau Data Hub Not approved 50 MW Not stated Not stated
Keel Sherbrooke, Bunker Operating 48 MW 48 MW Not stated
eStruxture MTL-2 Operating 30 MW Not stated Not stated
Vantage Montreal III Operating 30 MW Not stated Not stated
Keel Sherbrooke, Léger Operating 30 MW 30 MW Not stated
HIVE Lachute Operating 30 MW 30 MW Not stated
Cologix MTL9 Operating 25 MW Not stated Not stated
Keel Baie-Comeau Operating 22 MW 22 MW Not stated
Cologix MTL8 Operating 21 MW Not stated Not stated
Keel Sherbrooke, Garlock Operating 18 MW 18 MW Not stated
Keel Magog Operating 10 MW 10 MW Not stated
Google Beauharnois Data Center Announced Not stated Not stated Not stated
OVHcloud BHS Campus Operating Not stated Not stated Not stated
Microsoft Lévis Data Centre Construction Not stated Not stated Not stated
Microsoft Donnacona Data Centre Construction Not stated Not stated Not stated
Microsoft L’Ancienne-Lorette Data Centre Construction Not stated Not stated Not stated

Announced is what the company has said it will build. Energized is what is drawing power today. This is the list of projects we follow, not every project in the province.


Updated 2026-10-13.