HIVE Lachute
HIVE Digital / Lachute, QC
Operating
30 MW
announced
30 MW
energized
Fully energized against what was announced.
A 30 MW bitcoin mine in a building HIVE leases until June 2028, supplied by Hydro-Québec through the landlord's account. Its waste heat warms a swimming-pool factory next door. HIVE bought the operation from Cryptologic in 2020.
- Power path
- Grid
- Setup
- Hydro grid, bitcoin mining, waste heat reused next door
- Utility
- Hydro-Québec
- Connection request
- Not stated
- Target online
- Not stated
- Announced
- Not stated
Getting power in Quebec
Ministerial authorization. The Quebec record covers how projects get power there and what is changing.
Sources
- HIVE Digital Technologies Ltd. Form 10-K, fiscal year ended March 31, 2026
- Operations: HIVE Digital Technologies
Other tracked projects in Quebec
- QScale Q01 Campus QScale · 142 MW · Operating
- Vantage Quebec City Campus Vantage Data Centers · 86 MW · Construction
- Gatineau Data Hub AVAIO Digital Partners / Société immobilière ADAM · 50 MW · Not approved
- Keel Sherbrooke, Bunker Keel Infrastructure (formerly Bitfarms) · 48 MW · Operating
- eStruxture MTL-2 eStruxture · 30 MW · Operating
- Vantage Montreal III Vantage Data Centers · 30 MW · Operating
- Keel Sherbrooke, Léger Keel Infrastructure (formerly Bitfarms) · 30 MW · Operating
- Cologix MTL9 Cologix · 25 MW · Operating
Updated 2026-10-15.