Microsoft L’Ancienne-Lorette Data Centre

Microsoft / L'Ancienne-Lorette, QC

Construction

Not stated

announced

0 MW

energized

Construction started in June 2024. Generator tests were finished in early 2026, the substation transformers arrived in March 2026, and substation commissioning is set for autumn 2026. Microsoft expects construction to finish in early 2027 but has not given an opening date.


Power path
Grid
Setup
Hydro grid, Azure Canada East
Utility
Hydro-Québec
Connection request
Not stated
Target online
Not stated
Announced
2023-11-22

Getting power in Quebec

Ministerial authorization. The Quebec record covers how projects get power there and what is changing.