Milton Hyperscale Data Centre (proposed, near Halton Hills Generating Station)

Logistics Land Investments (TPA Group) / Milton (farmland near Halton Hills Generating Station)

Announced

720 MW

announced

0 MW

energized

None of it is drawing power yet.

  1. 2026-03-02 Announced
  2. 2028 Developer target stated by the developer, not a filed date

Power path
Grid
Generation tech
hyperscale data centre
Utility
IESO / Alectra Utilities
Queue reference
Milton TS interconnection (interconnection.fyi tracks a related 250+MW 'Datacenters Milton-Substation' entry, proposed operational 2028)
Target online
2028
Announced
2026-03-02
Verification
multiple
Coordinate
43.5183, -79.8774 (town)

Getting power in Ontario

Open door dressed in new gatekeeping: government now picks winners before IESO's technical process even starts.

The full Ontario record, with the route to power, the binding constraint and every dated policy event.

Sources

No formal planning application had been filed as of the National Observer report, which also found no evidence the firm has built a hyperscale data centre before or owns the land outright. Capacity figures conflict: 720 MW is the developer’s own claim and is shown as an upper bound, against a grid-tracker figure of 250 MW or more. As of February 2026 the status was reportedly moved from active to on hold.

Other tracked projects in Ontario


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com

External document

This is hosted by the publisher, not by McCord, and your browser may download it rather than open it in a tab.

Open the document