Steelport AI Data Centre Campus (former Stelco lands)
Slate Asset Management (with Digital Research Alliance of Canada) / Hamilton waterfront, former Stelco steelworks lands
Announced
400 MW
announced
0 MW
energized
None of it is drawing power yet.
- Power path
- Grid
- Generation tech
- publicly-oriented AI compute ('AI Factory') for Canadian academic/research data
- Utility
- Alectra Utilities
- Queue reference
- IESO connection request (originally 180MW, updated to 400MW)
- Target online
- Not stated
- Announced
- 2025-01-01
- Verification
- multiple
- Coordinate
- 43.2765, -79.7995 (region)
Getting power in Ontario
Open door dressed in new gatekeeping: government now picks winners before IESO's technical process even starts.
The full Ontario record, with the route to power, the binding constraint and every dated policy event.
Sources
- What you need to know about the proposed AI data centre in Hamilton
- Hamilton rejects plan to partition Stelco lands for AI data centre
- Data centre proposal on former steelmaking site sparks public backlash in Hamilton
- Hamilton-owned corporation signs NDA over proposed AI data centre
Slate owns 800 acres of Hamilton waterfront and is proposing an 88-hectare campus. Hamilton’s Committee of Adjustment unanimously denied a land-severance application on 4 June 2026, and council voted 15-1 to advance a citywide moratorium. The severance denial blocks this particular approval path rather than the project outright, so it is held at announced.
Other tracked projects in Ontario
- Milton Hyperscale Data Centre (proposed, near Halton Hills Generating Station) Logistics Land Investments (TPA Group) · 720 MW · Announced
- BUZZ HPC Greater Toronto Area AI Gigafactory BUZZ High Performance Computing Inc. (subsidiary of HIVE Digital Technologies Ltd.) · 320 MW · Announced
- Validus Power Iroquois Falls Data Centre Validus Power Corp · 120 MW · Announced
- Ascent/Related Digital Cambridge Data Centre (17 Vondrau St, TOR1 campus) Ascent Corp / Related Digital / TowerBrook Capital Partners (JV) · 60 MW · Construction
- STACK Infrastructure Toronto Campus (TOR01, 3650 Danforth Ave) STACK Infrastructure · 56 MW · Operating
- Prologis Meadowvale Business Park Data Centre Prologis · 40 MW · Announced
- Compass Datacenters Toronto Campus (75-77 Fima Crescent, Etobicoke) Compass Datacenters · 30 MW · Operating
- Validus Power North Bay Data Centre Validus Power Corp · 30 MW · Announced
Last verified 2026-08-01. Corrections: sam@mccordinvestments.com