Compass Toronto Campus

Compass Datacenters / Etobicoke, Toronto, ON

Operating

27 MW

announced

10 MW

energized

37% of what was announced is drawing power.

A converted logistics building. Compass said the first building would support 27 MW of IT load, with the first 10 MW done in late 2020.


Power path
Grid
Setup
Grid power
Utility
Toronto Hydro
Connection request
Not stated
Target online
Not stated
Announced
2020-05-05

Getting power in Ontario

Grid, provincial approval in draft. The Ontario record covers how projects get power there and what is changing.