STACK Infrastructure Toronto Campus (TOR01, 3650 Danforth Ave)

STACK Infrastructure / 3650 Danforth Ave, Scarborough, Toronto

Operating

56 MW

announced

8 MW

energized

14% of what was announced is drawing power.

  1. 2022-05-01 Announced
  2. 2026-Q2 Developer target stated by the developer, not a filed date

Power path
Grid
Generation tech
hyperscale/AI colocation, three diverse Toronto Hydro substations
Utility
Toronto Hydro
Queue reference
Not stated
Target online
2026-Q2
Announced
2022-05-01
Verification
multiple
Coordinate
43.6883, -79.2891 (site)

Getting power in Ontario

Open door dressed in new gatekeeping: government now picks winners before IESO's technical process even starts.

The full Ontario record, with the route to power, the binding constraint and every dated policy event.

Sources

Phase 1, 8 MW, delivered and in service September 2023. Phases 2 and 3, a further 48 MW to reach 56 MW in total, remain in expansion and proposal stage, with active community opposition including a local councillor and more than 4,800 petitioners as of July 2026.

Other tracked projects in Ontario


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com