STACK Toronto Campus

STACK Infrastructure / Scarborough, Toronto, ON

Operating

56 MW

announced

8 MW

energized

14% of what was announced is drawing power.

The first 8 MW has been running since September 2023. STACK wants to add two buildings and take the campus to 56 MW, and the plan is going through Toronto's site plan review. In July 2026 Toronto council voted 25 to 0 for extra scrutiny of the expansion, including an independent noise review.


Power path
Grid
Setup
Grid power from three Toronto Hydro substations
Utility
Toronto Hydro
Connection request
Not stated
Target online
Not stated
Announced
2022-05-01

Getting power in Ontario

Grid, provincial approval in draft. The Ontario record covers how projects get power there and what is changing.