Bell AI Fabric, two more BC sites
Bell Canada / British Columbia, sites not named
Announced
400 MW
announced
0 MW
energized
None of it is drawing power yet.
Two more Bell AI Fabric sites in British Columbia, which Bell says total more than 400 MW and are in advanced planning. Bell has not named the locations.
Not shown on the map. No location has been disclosed for this project beyond British Columbia, sites not named. Its megawatts are counted in every total on this site; only the dot is withheld, because placing one would assert a site nobody has stated.
- Power path
- Grid
- Setup
- Grid power
- Utility
- BC Hydro
- Connection request
- Not stated
- Target online
- Not stated
- Announced
- 2025-05-28
Getting power in British Columbia
Competitive call. The British Columbia record covers how projects get power there and what is changing.
Sources
Other tracked projects in British Columbia
- IREN Mackenzie IREN · 80 MW · Operating
- DMG Christina Lake DMG Blockchain Solutions · 75 MW · Operating
- IREN Prince George IREN · 50 MW · Operating
- IREN Canal Flats IREN · 30 MW · Operating
- Bell AI Fabric Kamloops, TRU campus Bell Canada with Thompson Rivers University · 26 MW · Construction
- Bell AI Fabric Kamloops, second site Bell Canada · 26 MW · Announced
- Bell AI Fabric Kamloops Bell Canada with Groq · 7 MW · Operating
- Bell AI Fabric Merritt Bell Canada (Buzz HPC as tenant) · 7 MW · Construction
Updated 2026-10-14.