British Columbia

BC Hydro; British Columbia Utilities Commission regulates rates

Route to power. Competitive call. B.C. Reg. 8/2026 caps new data centre power in BC Hydro's service area at 400 MW over two years and hands it out by competitive call. The first call drew 15 applications for close to 800 MW.


How you connect

Since 1 February 2026, a new data centre in BC Hydro’s area gets power only by winning BC Hydro’s Call for Demand. The 2026 call took projects of 10 to 145 MW, asked for bid security of $25,000 per MW, and closed on 9 March. It drew 15 applications for close to 800 MW. With a provincial election called, BC Hydro has delayed the results until after the government transition later this year. The details are on its emerging industries page.

Winning lets a project go on to BC Hydro’s connection studies; it is not a power contract. Projects under 10 MW, and those that had signed a facilities study agreement or paid a distribution design deposit before 1 February 2026, use the standard process.

How the cap splits

Over the first two years, up to 100 MW for conventional data centres and 300 MW for AI data centres, falling to 50 MW and 150 MW in the third year. No single project can take more than 145 MW.

Bringing your own power

Legal, and the only uncapped route in BC Hydro’s service area. The call does not cover FortisBC’s service area in the southern interior, though BC Hydro cannot sell FortisBC extra power for data centres.

What it costs

There is no separate data centre rate. Winning projects pay at least 10% more than the normal demand and energy charges.

What has happened

  1. With an election called, BC Hydro delays its Call for Demand results
  2. New data centre rules do not reach FortisBC’s service area
  3. BC Hydro opens its first Call for Demand, capped at 400 MW over two years

Projects we track

Project Status Announced Energized Target online
Bell AI Fabric, two more BC sites Announced 400 MW Not stated Not stated
IREN Mackenzie Operating 80 MW 80 MW 2022
DMG Christina Lake Operating 75 MW Not stated 2026-Q4
IREN Prince George Operating 50 MW 50 MW 2022
IREN Canal Flats Operating 30 MW 30 MW 2019
Bell AI Fabric Kamloops, TRU campus Construction 26 MW Not stated 2027
Bell AI Fabric Kamloops, second site Announced 26 MW Not stated 2027
Bell AI Fabric Kamloops Operating 7 MW 7 MW 2025-Q2
Bell AI Fabric Merritt Construction 7 MW Not stated 2027
Telus Kamloops AI Factory Announced Not stated Not stated 2026
Telus AI Data Centre, Mount Pleasant Announced Not stated Not stated 2026
Telus AI Data Centre, 150 West Georgia Announced Not stated Not stated 2029

Announced is what the company has said it will build. Energized is what is drawing power today. This is the list of projects we follow, not every project in the province.


Updated 2026-10-13.