IREN Prince George Data Center
IREN Ltd. (formerly Iris Energy) / Prince George, BC
Operating
50 MW
announced
50 MW
energized
Fully energized against what was announced.
- Power path
- Grid
- Generation tech
- Bitcoin ASIC mining, converting to AI/GPU cloud compute Hosts IREN's AI Cloud GPU fleet.
- Utility
- BC Hydro
- Queue reference
- Not stated
- Target online
- 2022
- Announced
- Not stated
- Verification
- press
- Coordinate
- 53.9171, -122.7497 (town)
Getting power in British Columbia
Effectively closed to unsolicited load: capacity is capped and allocated by competitive call, not first-come-first-served.
The full British Columbia record, with the route to power, the binding constraint and every dated policy event.
Sources
Part of IREN’s British Columbia portfolio, and the site the company describes as its most technically flexible in Canada. Running a mix of mining and AI workloads. The 50 MW figure is per IREN’s FY2025 10-K property table. Prince George hosts IREN’s entire AI Cloud GPU fleet, and its Q3 FY2026 10-Q reports that all AI Cloud Services revenue was generated in Canada. IREN does not disclose the split between AI and mining capacity at the site, so none is shown.
Other tracked projects in British Columbia
- Bell AI Fabric -- two additional undisclosed BC sites Bell Canada · 400 MW · Announced
- Telus Kamloops sovereign AI data centre (expansion) Telus, in partnership with Government of Canada · 85 MW · Announced
- IREN Mackenzie Data Center IREN Ltd. (formerly Iris Energy) · 80 MW · Operating
- DMG Blockchain Christina Lake Data Center DMG Blockchain Solutions Inc. · 65 MW · Construction
- IREN Canal Flats Data Center IREN Ltd. (formerly Iris Energy) · 30 MW · Operating
- Bell AI Fabric Kamloops -- Thompson Rivers University site Bell Canada · 26 MW · Announced
- Bell AI Fabric Kamloops Bell Canada, with Groq (inference partner) · 7 MW · Operating
- Bell AI Fabric Merritt (with Buzz HPC) Bell Canada; Buzz HPC (subsidiary of HIVE Digital Technologies) as GPU tenant · 7 MW · Announced
Last verified 2026-08-01. Corrections: sam@mccordinvestments.com