DMG Christina Lake
DMG Blockchain Solutions / Christina Lake, BC
Operating
75 MW
announced
Not stated
energized
A bitcoin mine that DMG plans to convert to AI hosting. The site has 75 MW of power, 15 MW firm and 60 MW that the utility can cut. In June 2026 DMG signed a non-binding letter of intent for 50 MW with one tenant and keeps mining bitcoin until a final deal is signed.
- 2026-02-10 Announced
- 2026-Q4 Developer target
- Power path
- Grid
- Setup
- Grid power, bitcoin mining converting to AI hosting
- Utility
- FortisBC
- Connection request
- Not stated
- Target online
- 2026-Q4
- Announced
- 2026-02-10
Getting power in British Columbia
Competitive call. The British Columbia record covers how projects get power there and what is changing.
Sources
- DMG Blockchain Solutions Announces 75 MW Utility Approval Expanding Christina Lake Data Center Power
- DMG Blockchain Solutions Inc. Announces 50-Megawatt AI Data Center Letter of Intent
Other tracked projects in British Columbia
- Bell AI Fabric, two more BC sites Bell Canada · 400 MW · Announced
- IREN Mackenzie IREN · 80 MW · Operating
- IREN Prince George IREN · 50 MW · Operating
- IREN Canal Flats IREN · 30 MW · Operating
- Bell AI Fabric Kamloops, TRU campus Bell Canada with Thompson Rivers University · 26 MW · Construction
- Bell AI Fabric Kamloops, second site Bell Canada · 26 MW · Announced
- Bell AI Fabric Kamloops Bell Canada with Groq · 7 MW · Operating
- Bell AI Fabric Merritt Bell Canada (Buzz HPC as tenant) · 7 MW · Construction
Updated 2026-10-14.