DMG Blockchain Christina Lake Data Center

DMG Blockchain Solutions Inc. / Christina Lake, BC

Construction

65 MW

announced

0 MW

energized

None of it is drawing power yet.

  1. 2026-02-10 Announced
  2. 2026-Q4 Developer target stated by the developer, not a filed date

Power path
Grid
Generation tech
Bitcoin mining converting to AI/HPC colocation (hydro direct liquid cooling; SCIF-rated prefabricated units)
Utility
BC Hydro
Queue reference
Not stated
Target online
2026-Q4
Announced
2026-02-10
Verification
multiple
Coordinate
49.0834, -118.2062 (town)

Getting power in British Columbia

Effectively closed to unsolicited load: capacity is capped and allocated by competitive call, not first-come-first-served.

The full British Columbia record, with the route to power, the binding constraint and every dated policy event.

Sources

Mining since 2018; company-stated site capacity 65MW. Physical delivery of 2MW SCIF-rated prefab units (April 2026) is concrete build-out evidence supporting 'construction'. 50MW LOI (June 2026) is a subset of, not additive to, site capacity. Regional District of Kootenay Boundary reportedly flags unresolved bylaw infringements (per a CBC report that could not be independently fetched -- paywalled).

Other tracked projects in British Columbia


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com

External document

This is hosted by the publisher, not by McCord, and your browser may download it rather than open it in a tab.

Open the document