55H High-Density Colocation Data Centre

55H / CORE Data Centres / 55 Hereford St, Brampton

Operating

20 MW

announced

0 MW

energized

None of it is drawing power yet.

  1. 2025-03-05 Announced
  2. 2026-H1 Developer target stated by the developer, not a filed date

Power path
Grid
Generation tech
high-density AI colocation, liquid cooling, up to 130kW/rack
Utility
Alectra Utilities
Queue reference
Not stated
Target online
2026-H1
Announced
2025-03-05
Verification
multiple
Coordinate
43.6874, -79.7395 (site)

Getting power in Ontario

Open door dressed in new gatekeeping: government now picks winners before IESO's technical process even starts.

The full Ontario record, with the route to power, the binding constraint and every dated policy event.

Sources

215,000 sq ft, Tier III, phased build-out: 2.5 MW available in 2025, a further 2.5 MW in summer 2025 and 15 MW in the first half of 2026, for 20 MW in total. Those tranches are the schedule stated in the March 2025 announcement; no later source confirms they have been energized, so no operating capacity is shown yet.

Other tracked projects in Ontario


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com

External document

This is hosted by the publisher, not by McCord, and your browser may download it rather than open it in a tab.

Open the document