Burlington Data Centre (3110 South Service Rd)

Undisclosed applicant (agent: Powell Planning and Associates) / 3110 South Service Rd, Burlington (former Mother Tucker's / Tucker's Marketplace site)

Announced

20 MW

announced

0 MW

energized

None of it is drawing power yet.


Power path
Grid
Generation tech
air-cooled colocation/cloud data centre
Utility
Burlington Hydro
Queue reference
Not stated
Target online
Not stated
Announced
2026-07-06
Verification
public_filing
Coordinate
43.3213, -79.7857 (site)

Getting power in Ontario

Open door dressed in new gatekeeping: government now picks winners before IESO's technical process even starts.

The full Ontario record, with the route to power, the binding constraint and every dated policy event.

Sources

City of Burlington site-plan application deemed complete July 6, 2026, ~20MW total. City decision deadline September 4, 2026. Operator undisclosed.

Other tracked projects in Ontario


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com

External document

This is hosted by the publisher, not by McCord, and your browser may download it rather than open it in a tab.

Open the document