Map / ON
Verified 2026-08-01
Burlington Data Centre (3110 South Service Rd)
Undisclosed applicant (agent: Powell Planning and Associates) / 3110 South Service Rd, Burlington (former Mother Tucker's / Tucker's Marketplace site)
Announced
20 MW
announced
0 MW
energized
None of it is drawing power yet.
- Power path
- Grid
- Generation tech
- air-cooled colocation/cloud data centre
- Utility
- Burlington Hydro
- Queue reference
- Not stated
- Target online
- Not stated
- Announced
- 2026-07-06
- Verification
- public_filing
- Coordinate
- 43.3213, -79.7857 (site)
Getting power in Ontario
Open door dressed in new gatekeeping: government now picks winners before IESO's technical process even starts.
The full Ontario record, with the route to power, the binding constraint and every dated policy event.
Sources
- 3110 South Service Rd. - Current Development Projects
- Burlington councillors vote down data centre moratorium
City of Burlington site-plan application deemed complete July 6, 2026, ~20MW total. City decision deadline September 4, 2026. Operator undisclosed.
Other tracked projects in Ontario
- Milton Hyperscale Data Centre (proposed, near Halton Hills Generating Station) Logistics Land Investments (TPA Group) · 720 MW · Announced
- Steelport AI Data Centre Campus (former Stelco lands) Slate Asset Management (with Digital Research Alliance of Canada) · 400 MW · Announced
- BUZZ HPC Greater Toronto Area AI Gigafactory BUZZ High Performance Computing Inc. (subsidiary of HIVE Digital Technologies Ltd.) · 320 MW · Announced
- Validus Power Iroquois Falls Data Centre Validus Power Corp · 120 MW · Announced
- Ascent/Related Digital Cambridge Data Centre (17 Vondrau St, TOR1 campus) Ascent Corp / Related Digital / TowerBrook Capital Partners (JV) · 60 MW · Construction
- STACK Infrastructure Toronto Campus (TOR01, 3650 Danforth Ave) STACK Infrastructure · 56 MW · Operating
- Prologis Meadowvale Business Park Data Centre Prologis · 40 MW · Announced
- Compass Datacenters Toronto Campus (75-77 Fima Crescent, Etobicoke) Compass Datacenters · 30 MW · Operating
Last verified 2026-08-01. Corrections: sam@mccordinvestments.com