Yondr Toronto Data Center (TOR1)

Yondr Group / Toronto (Don Valley North)

Construction

27 MW

announced

0 MW

energized

None of it is drawing power yet.

  1. 2025-01-29 Announced
  2. 2026-Q2 Developer target stated by the developer, not a filed date

Power path
Grid
Generation tech
grid-fed colocation, closed-loop cooling (no evaporative water use)
Utility
Toronto Hydro
Queue reference
Not stated
Target online
2026-Q2
Announced
2025-01-29
Verification
multiple
Coordinate
43.7969, -79.3376 (town)

Getting power in Ontario

Open door dressed in new gatekeeping: government now picks winners before IESO's technical process even starts.

The full Ontario record, with the route to power, the binding constraint and every dated policy event.

Sources

Three sources all cover the same groundbreaking event and largely trace to the same company press release -- per independence rule, treat as ~1-2 independent confirmations, not three. Groundbreaking event itself (attended by a named city councillor) is adequate 'construction' evidence. No energization evidence yet.

Other tracked projects in Ontario


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com