Genesee Data Centre Project

Capital Power / Leduc County, AB (Genesee Generating Station, ~71 km southwest of Edmonton)

In queue

1.5 GW

announced

0 MW

energized

None of it is drawing power yet.

  1. 2024-06-26 Filed with the operator 1,500 MW filed
  2. 2025-07-30 Announced
  3. No date In service the operator has set no date

Power path
Hybrid
Generation tech
Co-located with the 1,800 MW Genesee Generating Station, repowered to natural gas combined cycle. CCUS and SMR described as future options.
Utility
AESO
Queue reference
P2942 Genesee Data Center 1 MPC Load (AESO, Wabamun planning area, 1,000 MW DTS, ISD Under Review, applied 2024-06-26); P2946 Genesee Data Center 2 MPC Load (AESO, Wabamun planning area, 500 MW DTS, ISD Under Review, applied 2024-08-08)
Target online
Not stated
Announced
2025-07-30
Verification
multiple
Coordinate
53.3167, -114.3 (region)

Filed with the system operator

What this project has on file with AESO, which is a different act from announcing it. Transcribed from AESO's published connection list.

Reference Stage Filed In service Status
P2942 [object Object] 1,000 MW No date ISD Under Review
P2946 [object Object] 500 MW No date ISD Under Review

2 entries totalling 1,500 MW filed, against 1.5 GW announced. Why those two figures differ.

Getting power in Alberta

Courting load loudly while the near-term connection queue is already spoken for.

The full Alberta record, with the route to power, the binding constraint and every dated policy event.

Sources

1,500 MW is the sum of the two AESO references filed for this campus, P2942 at 1,000 MW and P2946 at 500 MW, matching Capital Power's own description of a 1.0 to 1.5 GW campus made up of one 1,000 MW and one 500 MW facility. Neither reference is scheduled: both sit in ISD Under Review with no AESO in-service date. Capital Power told Global News in July 2025 that it would not pursue a smaller interim project under AESO's 1,200 MW Phase 1 cap and would wait for a later allocation phase, which is consistent with both references being undated. The 2028 target is the company’s, not the system operator’s. The coordinate is the Genesee Generating Station rather than a disclosed data hall location: Leduc County has given written support and made bylaw changes, but the specific parcel is not public.

Other tracked projects in Alberta


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com

External document

This is hosted by the publisher, not by McCord, and your browser may download it rather than open it in a tab.

Open the document