Alberta

AESO (Alberta Electric System Operator); Alberta Utilities Commission is the regulator

Route to power. Bring your own generation. Under the Data Centre Regulation, AR 117/2026, AESO has to deal with a project that brings its own generation before one that does not. Building new generation is the way in. The 1,200 MW of interim grid capacity is fully allocated.

AESO publishes a project-level list. Its October 2026 edition shows 26.8 GW of data centre load requested, 20.7 GW of it with no connection date. See the list.


Who has grid capacity

AESO capped grid connections for large loads due in service in 2027 and 2028 at 1,200 MW, and shared it out in 2025. Two projects got all of it: GLDC Load at 970 MW and Keephills Data Centre Phase I at 230 MW, both with contracts signed by November 2025. Most other data centre requests on AESO’s list, about 20 GW, have no connection date.

Bringing your own generation

This is now the way in. Under Alberta’s Data Centre Regulation, a data centre of 75 MW or more that brings its own generation is dealt with before one that does not. Fully off-grid sites fall outside the regulation and pay no levy.

AESO proposed the process in June 2026: intakes of about six weeks roughly every nine months, a commitment of $15,000 per MW, connection studies of three to six months, and gas generation sized to the full load. In September it said the final process and the first intake would come this fall. Until then those terms are a proposal. AESO posts updates on its engagement page.

AESO’s October 2026 list added nine data centre requests that bring their own gas or battery power, about 4,300 MW in total, with requested in-service dates from late 2027 to 2030. They are the first data centre requests on the list paired with their own generation.

How you connect

Every load applies to AESO with a System Access Service Request, asking for contract capacity under its demand transmission rate. Once accepted, the project gets a number and appears on AESO’s monthly Connection Project List.

What it costs

A levy of up to 2% on the value of computing equipment, lower for sites that supply their own power. It is fully deductible against Alberta corporate income tax. Under Bill 8, data centres will pay for the transmission upgrades they need rather than other ratepayers; the details have not been set. There is no separate data centre electricity rate.

How long it takes

AESO publishes no figure. Its own list gives the 970 MW project an application date of May 2024, 60 MW in service in May 2027 and the full load in September 2030. That is about 3 years to first power and 6.3 years to the full load. These are the in-service dates that project requested. The 230 MW project shows no date.

Power plants built for data centres

Two gas plants for Beacon AI Centers are before the Alberta Utilities Commission: Indus in Rocky View County, 1,494 MW supplying about 1,200 MW of data halls, and Heartland in Sturgeon County, 920 MW supplying about 800 MW. Heartland went through a written hearing that closed in July 2026, and Indus had an oral hearing from 18 August. Neither has a decision yet. On 17 August the commission denied a third, the gas plant for Synapse’s off-grid data centre near Olds, finding it too close to the community.

What has happened

  1. AESO says the bring-your-own-generation process and first intake will come this fall
  2. AUC oral hearing opens on Beacon’s 1,494 MW Indus gas plant for data centres
  3. AUC denies the gas plant for Synapse’s data centre near Olds
  4. Written hearing closes on Beacon’s 920 MW Heartland gas plant
  5. AESO publishes its connection requirements for data centres
  6. Alberta’s Data Centre Regulation puts projects with their own generation first
  7. Bill 8 receives royal assent: data centres will pay for their own transmission upgrades

Projects we track

Project Status Announced Energized Target online
Genesee Data Centre Filed for connection 1,500 MW Not stated Not stated
Wonder Valley AI Data Centre Park, Phase 1 Announced 1,400 MW Not stated Not stated
Wild Rose Data Centre Filed for connection 1,300 MW Not stated Not stated
Beacon AI Hub, Indus Announced 1,200 MW Not stated Not stated
Meta Data Centre, Sturgeon County Construction 1,000 MW Not stated Not stated
Synapse Olds Data Centre Not approved 1,000 MW Not stated Not stated
Malachite One Data Centre Announced 1,000 MW Not stated 2028
Beacon AI Hub, Heartland Filed for connection 800 MW Not stated Not stated
Mihta Askiy Data Centre Announced 650 MW Not stated Not stated
Beacon AI Data Centre Hub, Chestermere Announced 400 MW Not stated Not stated
TNE and Data District Data Centres, Phase 1 Announced 240 MW Not stated Not stated
Keephills Data Centre Filed for connection 230 MW Not stated Not stated
Black Bear Power Project Filed for connection 200 MW Not stated 2028-Q3
Northern Forge Power Project Announced 200 MW Not stated 2028
StratGrid Project Wheatland Announced 200 MW Not stated Not stated
Crusoe AI Data Centre, Myers Energy Park Announced 170 MW Not stated Not stated
Crusoe AI Data Centre, Alsike Energy Park Announced 170 MW Not stated Not stated
Bitdeer Fox Creek Facility Construction 101 MW Not stated 2027-Q4
eStruxture CAL-3 Construction 90 MW Not stated 2026
Captus Generation AI Data Centre Filed for connection 75 MW Not stated Not stated
Hut 8 Medicine Hat Facility Operating 67 MW 67 MW Not stated
Hut 8 Drumheller Operating 42 MW 42 MW Not stated
Blindman Industrial Park AI Data Centre Construction 10 MW Not stated Not stated
AWS Canada West Region Operating Not stated Not stated 2023
Rocky View Technology Park Not approved Not stated Not stated Not stated
Goldfinch Technology Park Announced Not stated Not stated Not stated
Travers AI Data Centre Campus Announced Not stated Not stated Not stated

Announced is what the company has said it will build. Energized is what is drawing power today. This is the list of projects we follow, not every project in the province.

Alberta · AR 117/2026 · current as of 9 June 2026

Alberta now puts data centres that bring their own generation to the front of the queue.

The Data Centre Regulation, AR 117/2026, sets the rules now that the interim 1,200 MW is used up. A project that brings its own generation is processed first; everyone else is subject to conditions AESO sets. The binding constraint has moved off the wires and onto plant, and AESO calls the route bring your own generation.

The clauses that decide it

Binding law

s.2 A large data centre is 75 MW or more, and the line can move down
At or above 75 MW of maximum demand a project is a "large data centre". That figure is a default rather than a floor: s.2(2) lets AESO set a lower threshold on reliability or adequacy grounds, so sizing just under it is not a durable way out of the regime.
s.6 Tethered requests are processed first
AESO must prioritise processing a request from a tethered data centre over one from a large data centre that is not tethered. This is the regulation's actual operating mechanism: untethered load is deprioritised, not prohibited.
s.5 Being tethered means bringing incremental generation
AESO may designate a data centre tethered to generating units capable of supplying the transmission system at a rate at least equal to its maximum demand. The supply offsets into the common pool rather than being wired privately to the load, but it must be incremental: a proposed unit must be new, and an existing unit qualifies only where its service is being modified upward or it has been declared under the relevant provisions.
s.7 Financing and water licences can gate service
AESO may set criteria covering site control, municipal zoning approvals, financing and the issuance of permits or water licences. Meeting them is a condition of service being provided.
s.9(5) Bridged supply runs three years at the outside
Where AESO grants bridged service, grid energy taken before the tethered generation runs, it may run for a maximum of three years from when it is first provided. Bridging is discretionary throughout: s.9(1) says "may provide", and s.9(2) gates it on AUC approval of the tethered units.
s.10 Curtailment falls on data centres first, in two stages
On a determination of inadequate supply, bridged data centres reduce demand before all other market participants. Separately, where mandatory load shedding is required, every large data centre reduces before the rest of the market. The two limbs have different triggers and a non-bridged site is exposed only to the second.
s.3 Adjacent sites can be treated as one, if they are related
AESO may aggregate two or more data centres into one where they are physically or operationally integrated and on the same or adjacent parcels, AND a common person or affiliate is receiving or requesting service for them. Both limbs are required, so unrelated neighbours are not captured.
s.12 The regime is reviewed by 2030 and expires in 2035
The regulation must be reviewed on or before 31 May 2030 and expires on 31 May 2035. Anything underwritten against it should be underwritten against that clock.

Proposed, not yet law

AESO published the Phase 2A design on 26 June 2026. Its update of 8 September 2026 says the process documents and application intake, earlier expected in August, will be posted and open this fall. No date is given. These mechanics are a proposal and are marked as such because most summaries report them as settled (Osler):

  • An intake window of six weeks. AESO’s proposal plans intakes roughly every nine months, run in parallel with cluster studies. No date for a second intake is published.
  • A commitment payment of C$15,000 per MW of requested service, invoiced at intake close and proposed as potentially refundable.
  • A system-wide bridging pool of 1,600 MW, reassessed at each intake.
  • Tethered generation limited to gas-fired plant in the first cycle, described as provisional and reviewable.

What it means for a build

Tethering buys processing priority and, at AESO's discretion, up to three years of bridged supply while the plant is built. Going without it means waiting behind everyone who did, on conditions AESO sets. Both roads end at the same place: securing generating equipment against a date.

Regulation text read directly from Alberta King's Printer, current as of 9 June 2026. Phase 2A mechanics from AESO's published Large Load Integration materials. Where a secondary summary and the regulation disagree, the regulation is used.


Updated 2026-10-13.