Alberta
AESO (Alberta Electric System Operator); Alberta Utilities Commission is the regulator
Route to power. Bring your own generation. Under the Data Centre Regulation, AR 117/2026, AESO has to deal with a project that brings its own generation before one that does not. Building new generation is the way in. The 1,200 MW of interim grid capacity is fully allocated.
AESO publishes a project-level list. Its October 2026 edition shows 26.8 GW of data centre load requested, 20.7 GW of it with no connection date. See the list.
Who has grid capacity
AESO capped grid connections for large loads due in service in 2027 and 2028 at 1,200 MW, and shared it out in 2025. Two projects got all of it: GLDC Load at 970 MW and Keephills Data Centre Phase I at 230 MW, both with contracts signed by November 2025. Most other data centre requests on AESO’s list, about 20 GW, have no connection date.
Bringing your own generation
This is now the way in. Under Alberta’s Data Centre Regulation, a data centre of 75 MW or more that brings its own generation is dealt with before one that does not. Fully off-grid sites fall outside the regulation and pay no levy.
AESO proposed the process in June 2026: intakes of about six weeks roughly every nine months, a commitment of $15,000 per MW, connection studies of three to six months, and gas generation sized to the full load. In September it said the final process and the first intake would come this fall. Until then those terms are a proposal. AESO posts updates on its engagement page.
AESO’s October 2026 list added nine data centre requests that bring their own gas or battery power, about 4,300 MW in total, with requested in-service dates from late 2027 to 2030. They are the first data centre requests on the list paired with their own generation.
How you connect
Every load applies to AESO with a System Access Service Request, asking for contract capacity under its demand transmission rate. Once accepted, the project gets a number and appears on AESO’s monthly Connection Project List.
What it costs
A levy of up to 2% on the value of computing equipment, lower for sites that supply their own power. It is fully deductible against Alberta corporate income tax. Under Bill 8, data centres will pay for the transmission upgrades they need rather than other ratepayers; the details have not been set. There is no separate data centre electricity rate.
How long it takes
AESO publishes no figure. Its own list gives the 970 MW project an application date of May 2024, 60 MW in service in May 2027 and the full load in September 2030. That is about 3 years to first power and 6.3 years to the full load. These are the in-service dates that project requested. The 230 MW project shows no date.
Power plants built for data centres
Two gas plants for Beacon AI Centers are before the Alberta Utilities Commission: Indus in Rocky View County, 1,494 MW supplying about 1,200 MW of data halls, and Heartland in Sturgeon County, 920 MW supplying about 800 MW. Heartland went through a written hearing that closed in July 2026, and Indus had an oral hearing from 18 August. Neither has a decision yet. On 17 August the commission denied a third, the gas plant for Synapse’s off-grid data centre near Olds, finding it too close to the community.
What has happened
- AESO says the bring-your-own-generation process and first intake will come this fall
- AUC oral hearing opens on Beacon’s 1,494 MW Indus gas plant for data centres
- AUC denies the gas plant for Synapse’s data centre near Olds
- Written hearing closes on Beacon’s 920 MW Heartland gas plant
- AESO publishes its connection requirements for data centres
- Alberta’s Data Centre Regulation puts projects with their own generation first
- Bill 8 receives royal assent: data centres will pay for their own transmission upgrades
Projects we track
| Project | Status | Announced | Energized | Target online |
|---|---|---|---|---|
| Genesee Data Centre | Filed for connection | 1,500 MW | Not stated | Not stated |
| Wonder Valley AI Data Centre Park, Phase 1 | Announced | 1,400 MW | Not stated | Not stated |
| Wild Rose Data Centre | Filed for connection | 1,300 MW | Not stated | Not stated |
| Beacon AI Hub, Indus | Announced | 1,200 MW | Not stated | Not stated |
| Meta Data Centre, Sturgeon County | Construction | 1,000 MW | Not stated | Not stated |
| Synapse Olds Data Centre | Not approved | 1,000 MW | Not stated | Not stated |
| Malachite One Data Centre | Announced | 1,000 MW | Not stated | 2028 |
| Beacon AI Hub, Heartland | Filed for connection | 800 MW | Not stated | Not stated |
| Mihta Askiy Data Centre | Announced | 650 MW | Not stated | Not stated |
| Beacon AI Data Centre Hub, Chestermere | Announced | 400 MW | Not stated | Not stated |
| TNE and Data District Data Centres, Phase 1 | Announced | 240 MW | Not stated | Not stated |
| Keephills Data Centre | Filed for connection | 230 MW | Not stated | Not stated |
| Black Bear Power Project | Filed for connection | 200 MW | Not stated | 2028-Q3 |
| Northern Forge Power Project | Announced | 200 MW | Not stated | 2028 |
| StratGrid Project Wheatland | Announced | 200 MW | Not stated | Not stated |
| Crusoe AI Data Centre, Myers Energy Park | Announced | 170 MW | Not stated | Not stated |
| Crusoe AI Data Centre, Alsike Energy Park | Announced | 170 MW | Not stated | Not stated |
| Bitdeer Fox Creek Facility | Construction | 101 MW | Not stated | 2027-Q4 |
| eStruxture CAL-3 | Construction | 90 MW | Not stated | 2026 |
| Captus Generation AI Data Centre | Filed for connection | 75 MW | Not stated | Not stated |
| Hut 8 Medicine Hat Facility | Operating | 67 MW | 67 MW | Not stated |
| Hut 8 Drumheller | Operating | 42 MW | 42 MW | Not stated |
| Blindman Industrial Park AI Data Centre | Construction | 10 MW | Not stated | Not stated |
| AWS Canada West Region | Operating | Not stated | Not stated | 2023 |
| Rocky View Technology Park | Not approved | Not stated | Not stated | Not stated |
| Goldfinch Technology Park | Announced | Not stated | Not stated | Not stated |
| Travers AI Data Centre Campus | Announced | Not stated | Not stated | Not stated |
Announced is what the company has said it will build. Energized is what is drawing power today. This is the list of projects we follow, not every project in the province.
Alberta · AR 117/2026 · current as of 9 June 2026
Alberta now puts data centres that bring their own generation to the front of the queue.
The Data Centre Regulation, AR 117/2026, sets the rules now that the interim 1,200 MW is used up. A project that brings its own generation is processed first; everyone else is subject to conditions AESO sets. The binding constraint has moved off the wires and onto plant, and AESO calls the route bring your own generation.
The clauses that decide it
Binding law
- s.2 A large data centre is 75 MW or more, and the line can move down
- At or above 75 MW of maximum demand a project is a "large data centre". That figure is a default rather than a floor: s.2(2) lets AESO set a lower threshold on reliability or adequacy grounds, so sizing just under it is not a durable way out of the regime.
- s.6 Tethered requests are processed first
- AESO must prioritise processing a request from a tethered data centre over one from a large data centre that is not tethered. This is the regulation's actual operating mechanism: untethered load is deprioritised, not prohibited.
- s.5 Being tethered means bringing incremental generation
- AESO may designate a data centre tethered to generating units capable of supplying the transmission system at a rate at least equal to its maximum demand. The supply offsets into the common pool rather than being wired privately to the load, but it must be incremental: a proposed unit must be new, and an existing unit qualifies only where its service is being modified upward or it has been declared under the relevant provisions.
- s.7 Financing and water licences can gate service
- AESO may set criteria covering site control, municipal zoning approvals, financing and the issuance of permits or water licences. Meeting them is a condition of service being provided.
- s.9(5) Bridged supply runs three years at the outside
- Where AESO grants bridged service, grid energy taken before the tethered generation runs, it may run for a maximum of three years from when it is first provided. Bridging is discretionary throughout: s.9(1) says "may provide", and s.9(2) gates it on AUC approval of the tethered units.
- s.10 Curtailment falls on data centres first, in two stages
- On a determination of inadequate supply, bridged data centres reduce demand before all other market participants. Separately, where mandatory load shedding is required, every large data centre reduces before the rest of the market. The two limbs have different triggers and a non-bridged site is exposed only to the second.
- s.3 Adjacent sites can be treated as one, if they are related
- AESO may aggregate two or more data centres into one where they are physically or operationally integrated and on the same or adjacent parcels, AND a common person or affiliate is receiving or requesting service for them. Both limbs are required, so unrelated neighbours are not captured.
- s.12 The regime is reviewed by 2030 and expires in 2035
- The regulation must be reviewed on or before 31 May 2030 and expires on 31 May 2035. Anything underwritten against it should be underwritten against that clock.
Proposed, not yet law
AESO published the Phase 2A design on 26 June 2026. Its update of 8 September 2026 says the process documents and application intake, earlier expected in August, will be posted and open this fall. No date is given. These mechanics are a proposal and are marked as such because most summaries report them as settled (Osler):
- An intake window of six weeks. AESO’s proposal plans intakes roughly every nine months, run in parallel with cluster studies. No date for a second intake is published.
- A commitment payment of C$15,000 per MW of requested service, invoiced at intake close and proposed as potentially refundable.
- A system-wide bridging pool of 1,600 MW, reassessed at each intake.
- Tethered generation limited to gas-fired plant in the first cycle, described as provisional and reviewable.
What it means for a build
Tethering buys processing priority and, at AESO's discretion, up to three years of bridged supply while the plant is built. Going without it means waiting behind everyone who did, on conditions AESO sets. Both roads end at the same place: securing generating equipment against a date.
Regulation text read directly from Alberta King's Printer, current as of 9 June 2026. Phase 2A mechanics from AESO's published Large Load Integration materials. Where a secondary summary and the regulation disagree, the regulation is used.
Updated 2026-10-13.