Mihta Askiy Data Centre
Mihta Askiy Datacenter LP (Woodland Cree First Nation) / Northeast of Peace River, Northern Sunrise County, AB
Announced
650 MW
announced
0 MW
energized
None of it is drawing power yet.
A 650 MW gas power facility built to supply a new data centre on the former Carmon Creek oil sands site, majority-owned by Woodland Cree First Nation. The federal Impact Assessment Agency decided on 4 March 2026 that no federal assessment is needed.
- Power path
- Behind the fence
- Setup
- Gas turbines, simple cycle first, later combined cycle
- Utility
- Not stated
- Connection request
- Not stated
- Target online
- Not stated
- Announced
- 2025-12-11
Getting power in Alberta
Bring your own generation. The Alberta record covers how projects get power there and what is changing.
Sources
Other tracked projects in Alberta
- Genesee Data Centre Capital Power · 1.5 GW · Filed for connection
- Wonder Valley AI Data Centre Park, Phase 1 O'Leary Ventures · 1.4 GW · Announced
- Wild Rose Data Centre BHE Canada · 1.3 GW · Filed for connection
- Beacon AI Hub, Indus Beacon AI Centers · 1.2 GW · Announced
- Meta Data Centre, Sturgeon County Meta · 1.0 GW · Construction
- Synapse Olds Data Centre Synapse Data Center Inc. · 1.0 GW · Not approved
- Malachite One Data Centre Emerald Energy Technologies (Tourmaline Oil) · 1.0 GW · Announced
- Beacon AI Hub, Heartland Beacon AI Centers · 800 MW · Filed for connection
Updated 2026-10-14.