Meta Data Center (Sturgeon County)

Meta Platforms Inc. / Sturgeon County (Alberta's Industrial Heartland), AB

In queue

970 MW

announced

0 MW

energized

None of it is drawing power yet.

  1. 2024-05-14 Filed with the operator 1,800 MW filed
  2. 2026-07-08 Announced
  3. 2027-05-01 In service

Power path
Hybrid
Generation tech
grid supply (AESO Phase 1 large-load allocation) plus adjacent natural gas generation (Greenlight Electricity Centre; Capital Power 250MW supply agreement)
Utility
AESO
Queue reference
P2936 GLDC Load Phase 1.1 (AESO, Fort Saskatchewan planning area, 970 MW DTS, Active, first grid date 2027-05-01); P3151 GLDC Load Phase 1.2 (830 MW DTS, ISD Under Review)
Target online
Not stated
Announced
2026-07-08
Verification
multiple
Coordinate
53.75, -113.6 (region)

Filed with the system operator

What this project has on file with AESO, which is a different act from announcing it. Transcribed from AESO's published connection list.

Reference Stage Filed In service Status
P2936 [object Object][object Object] 970 MW 2027-05-01 Active
P3151 [object Object] 830 MW No date ISD Under Review

2 entries totalling 1,800 MW filed, against 970 MW announced. Why those two figures differ.

Getting power in Alberta

Courting load loudly while the near-term connection queue is already spoken for.

The full Alberta record, with the route to power, the binding constraint and every dated policy event.

Sources

Alberta's first gigawatt-scale hyperscale project. 1,750-acre campus, $13B+ investment. Capital Power's separate 250 MW, 10-year-plus supply agreement starts H2 2028; the adjacent 932 MW Greenlight Electricity Centre gas plant is targeted for H2 2030. Meta describes the data centre as online in 'two to three years' from July 2026 without naming a year, so no target date is shown. Capacity is stated at 970 MW, which is the load AESO has on file for P2936, one of only two Phase 1 allocations; press materials describe the campus at a rounded 1 GW. Also tracked in the Alberta Major Projects registry as Meta Data Center (id 12183).

Other tracked projects in Alberta


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com