Goldfinch Technology Park
Diode Ventures (Black & Veatch) / Near Carseland, Wheatland County, AB
Announced
Not stated
announced
0 MW
energized
A 575-acre data centre campus. In August 2026 Wheatland County council rezoned the land for industrial use on a 4 to 3 vote. Diode says it is working with AESO on how much power can be supplied and will pay for the grid upgrades.
- Power path
- Grid
- Setup
- Not stated
- Utility
- AESO
- Connection request
- Not stated
- Target online
- Not stated
- Announced
- 2026-09-03
Getting power in Alberta
Bring your own generation. The Alberta record covers how projects get power there and what is changing.
Sources
Other tracked projects in Alberta
- Genesee Data Centre Capital Power · 1.5 GW · Filed for connection
- Wonder Valley AI Data Centre Park, Phase 1 O'Leary Ventures · 1.4 GW · Announced
- Wild Rose Data Centre BHE Canada · 1.3 GW · Filed for connection
- Beacon AI Hub, Indus Beacon AI Centers · 1.2 GW · Announced
- Meta Data Centre, Sturgeon County Meta · 1.0 GW · Construction
- Synapse Olds Data Centre Synapse Data Center Inc. · 1.0 GW · Not approved
- Malachite One Data Centre Emerald Energy Technologies (Tourmaline Oil) · 1.0 GW · Announced
- Beacon AI Hub, Heartland Beacon AI Centers · 800 MW · Filed for connection
Updated 2026-10-14.