Blindman Industrial Park AI Data Centre
Havenz Smart Communities (Havenz Corp) / Blindman Industrial Park, Red Deer County, AB (near Blackfalds)
Construction
0 MW
announced
0 MW
energized
- 2025-10-07 Announced
- 2026 Developer target stated by the developer, not a filed date
- Power path
- Behind the fence
- Generation tech
- on-site heat and power plant (modular gas-fired generation)
- Utility
- Not stated
- Queue reference
- Not stated
- Target online
- 2026
- Announced
- 2025-10-07
- Verification
- multiple
- Coordinate
- 52.3773, -113.7844 (region)
Getting power in Alberta
Courting load loudly while the near-term connection queue is already spoken for.
The full Alberta record, with the route to power, the binding constraint and every dated policy event.
Sources
- Red Deer County approves data centre
- Construction accelerates at AI data centre near Red Deer
- Blindman Industrial Park AI Data Centre (Alberta Major Projects registry)
Water-less, ultra-low-noise, minimal-staff facility on a 120-acre site. Phase 1 is 10 MW of on-site generation and a 10,800 sq ft modular data centre, targeted for completion in October 2026, and is the only stage with concrete sourcing. A 240 MW-plus figure has been discussed as a long-term buildout target rather than a current project size, so it is not counted here. CEO Sunny Sarpal.
Other tracked projects in Alberta
- Genesee Data Centre Project Capital Power · 1.5 GW · In queue
- Wonder Valley AI Data Centre Park (Phase 1) O'Leary Ventures · 1.4 GW · Announced
- Beacon AI Hub — Indus (with Indus Project Thermal Power Plant) Beacon AI Centers / Indus Power Generation LP · 1.2 GW · Announced
- Synapse Olds Data Centre Synapse Data Center Inc. · 1.0 GW · Announced
- Meta Data Center (Sturgeon County) Meta Platforms Inc. · 970 MW · In queue
- Beacon AI Centers — Heartland Project Thermal Power Plant Heartland Power Generation LP (Beacon AI Centers) · 800 MW · Announced
- Black Bear Power Project (data centre power supply) Teton Digital LLC (formerly Kiwetinohk Energy Corp.) · 466 MW · Announced
- Beacon AI Data Centre Hub - Chestermere Beacon Data Centres (Beacon AI) · 400 MW · In queue
Last verified 2026-08-01. Corrections: sam@mccordinvestments.com