Blindman Industrial Park AI Data Centre

Havenz Smart Communities (Havenz Corp) / Blindman Industrial Park, Red Deer County, AB (near Blackfalds)

Construction

0 MW

announced

0 MW

energized

  1. 2025-10-07 Announced
  2. 2026 Developer target stated by the developer, not a filed date

Power path
Behind the fence
Generation tech
on-site heat and power plant (modular gas-fired generation)
Utility
Not stated
Queue reference
Not stated
Target online
2026
Announced
2025-10-07
Verification
multiple
Coordinate
52.3773, -113.7844 (region)

Getting power in Alberta

Courting load loudly while the near-term connection queue is already spoken for.

The full Alberta record, with the route to power, the binding constraint and every dated policy event.

Sources

Water-less, ultra-low-noise, minimal-staff facility on a 120-acre site. Phase 1 is 10 MW of on-site generation and a 10,800 sq ft modular data centre, targeted for completion in October 2026, and is the only stage with concrete sourcing. A 240 MW-plus figure has been discussed as a long-term buildout target rather than a current project size, so it is not counted here. CEO Sunny Sarpal.

Other tracked projects in Alberta


Last verified 2026-08-01. Corrections: sam@mccordinvestments.com

External document

This is hosted by the publisher, not by McCord, and your browser may download it rather than open it in a tab.

Open the document