Northern Forge Power Project

Teton Digital LLC / South of Fox Creek, AB

Announced

200 MW

announced

0 MW

energized

None of it is drawing power yet.

A $500M, 200 MW behind-the-meter gas project on 155 acres about 35 km south of Fox Creek. Teton says it plans 30 MW in the first half of 2027, 100 MW by the end of 2027 and 200 MW in 2028.

  1. 2026-07-14 Announced
  2. 2028 Developer target

Power path
Behind the fence
Setup
Gas plant on site
Utility
Not stated
Connection request
Not stated
Target online
2028
Announced
2026-07-14

Getting power in Alberta

Bring your own generation. The Alberta record covers how projects get power there and what is changing.