Keephills Data Centre

TransAlta, CPP Investments and Brookfield / Keephills, Parkland County, AB

Filed for connection

230 MW

announced

0 MW

energized

None of it is drawing power yet.

The other project given grid capacity in AESO's Phase 1, 230 MW in two 115 MW stages. Since September 2026 AESO has had no in-service date for either stage, nor for the later 165 MW and 466 MW phases at the site. TransAlta, CPP Investments and Brookfield are still working under a non-binding MOU.

  1. 2025-01-28 Filed with the operator 861 MW filed
  2. 2026-02-27 Announced
  3. No date In service the operator has set no date

Power path
Hybrid
Setup
Grid, beside TransAlta’s Keephills power plant
Utility
AESO
Connection request
AESO P3095 Keephills Data Centre Phase 2 (466 MW), P3083 Keephills Data Centre Phase 1.1 (230 MW), P3152 Keephills Data Centre Phase 1.2 (165 MW)
Target online
Not stated
Announced
2026-02-27

Filed with the system operator

From AESO's connection list.

Reference Stage Filed In service Status
P3095 EN1 466 MW No date No date yet
P3083
  • EN1 115 MW not scheduled
  • EN2 115 MW not scheduled
230 MW No date No date yet
P3152 EN1 165 MW No date No date yet

3 entries, 861 MW in total.

Getting power in Alberta

Bring your own generation. The Alberta record covers how projects get power there and what is changing.

Sources

Other tracked projects in Alberta


Updated 2026-10-14.